Previous Page  42 / 48 Next Page
Information
Show Menu
Previous Page 42 / 48 Next Page
Page Background

40

¦

MechChem Africa

March 2017

Products and industry news

Cummins Power Generation has pro-

vided a standby power solution to provide

back-up power for Ghana’s six major

airports. This major turnkey project was

undertakenonbehalf ofmain clientGhana

Airports Company Limited of Accra. The

back-uppowerwill support air transporta-

tion systems in Accra, Tamale, Suyani, and

Kumasi, Ho andWa.

An end-to-end solution was provided

tomeet theparticular requirementsof this

major new customer for Cummins Power

Generation. AlfredOtoo, projectmanager

for Cummins Ghana comments: “Our role

was comprehensive, from compiling the

tender package for the project all theway

through to supervising the installation,

SKF South Africa provided a turn-

key solution in order to assist

an OEM customer to reduce

lead times and streamline

planned downtime.

In addition to the long

lead times on seals for

their underground earth-

moving equipment, the

customerwas alsounhappy

with general service delivery

from its supplier and decided to

look for a single source supplier. The

logicalstepwastoapproachSKFasthe

customerwasalreadyusingSKFbearings

and happy with its service delivery.

SKF’s OEM division suggested the

Safety-helmet suspensions improve comfort

Painful compression headaches due

to safety helmets that do not fit

properlyarenowa thingof thepast

thanks to flush suspension tabs

on the latest MSA Fas-Trac

®

 III

ratchet suspensions, available

from MSA Africa for its V-Gard

range of safety helmets.

The latest suspensions can be ordered

pre-fitted on any MSA V-Gard helmet, or as

spares. “We have made it ‘painless’ for customers

to standardise on these new suspensions as there is no change in

part numbers for complete helmet assemblies.MSAFas-Trac III is the

answer to everyone’s safety-helmet requirements,” SurakshaMohun,

product marketing manager, MSA Africa, comments.

Inaddition,twodifferentsweatbandoptionsareavailable,depend-

ing on applicationor preference. These arePVC, perforatedwipeable

or sweat-wicking and replaceable foam, which is alsomachine-wash-

able. The foam sweatband is made from breathable fabric for direct

air permeation.MSAFas-Trac III boasts the largest sweatband surface

areaonany safetyhelmet, which improves perspirationabsorptionby

covering more of the headband and the wearer’s forehead.

“Extensive customer researchhas revealed that theMSAFas-Trac

IIIwheel-ratchetsuspensionispreferredbymostusersoverwhatthey

are currentlywearing,”Mohun continues. “This is because of themain

benefits of improvedhelmet comfort, retention and stability, with the

added advantage of easy single-handed adjustment.”

The premiumMSAFas-Trac III suspension also comeswith a lower

nape strap than any other protection helmet suspension, which im-

proves balance and means that the safety helmet stays on when the

wearer leans over.

Separating the ratchet from the neck also allows the comfort

pad to cradle the wearer’s head, increasing air flow. The ratchet has

a smooth rotation and an easy-grip knob that can be adjusted even

when the user is wearing gloves. Superior nape fit and compatibility

with other personal protective equipment is ensured by three levels

of height adjustment.

MSAFas-Trac III suspensions are available for all V-Gard industrial

safety helmets fromMSA Africa.

www.za.msasafety.com

Standby power solution for Ghana Airports Company

commissioning, and handing over.”

The scope of supply for this presti-

gious project was a C1100 D5, four C500

D5, and two C450 D5 units. In addition,

Cummins Power Generation supplied

1 600 A ACB, four GTEC 800 A transfer

switches, and four GTEC 630 A transfer

switches.

Ghana Airports Company Limited

also specified low noise levels, which

meant Cummins Power Generation had

to pay special attention to the ambient

environment. Another challenge associ-

atedwith this project was adhering to the

strict timelines of the various airports,

which meant that installation could only

be carried out when air traffic was low,

Turnkey solution of new generation seals

Speedi-Sleeve as the best sealing solution

for the earthmoving equipment. The new

generation Speedi-Sleeve, developed by

SKF, uses a proprietary stainless steel

material and manufacturing process that

gives an optimised seal counter-face sur-

face which minimises wear on both the

sleeve and sealing lip. The contact surface

iswear-resistant. Imperceptible lubricant

pockets enable the lubricant to reside on

the sleeve and thereby prevent dry run-

ning of the sealing lip that otherwise can

create excessive wear.

Thethin-walledSpeedi-Sleeveissimply

pushed in position over the worn area.

There is no shaft disassembly or machin-

ing involved, minimising costly downtime.

Furthermore, since the installation tool is

suppliedwith the sleeve, no special equip-

ment is required to fit the seals.

In addition to supplying the Speedi-

Sleeves, SKF also provided product train-

ing, assisted with planning of downtime

to replace worn seals and helped the

customer to achieve the goal of reducing

its supplier and vendor lists.

Thecustomer expressedgreat satisfac-

tion as now it conveniently deals with a

single source supplier for both seals and

bearings.SKF’sprofessionalandexpedient

service also impressed the customer; SKF

sales representatives assisted with back

orders and continue to hold regular plan-

ning meetings to ensure that the correct

products are on the customer’s shelves.

www.skf.co.za

usually between 01:00 and 04:00 am.

“We could not interfere with anything

in terms of potentially switching off any

live system. In addition, we had an excep-

tionally narrow window of opportunity,

when air traffic was minimal, for us to

execute the project,” Otoo says.

He concludes that this flagship proj-

ect was an excellent showcase for the

Cummins brand, which extended beyond

simply supplying products to actually

adding value to the client’s business. “We

managed the entire project, right from

the initial contract win, resulting in the

best possible solution for our client, in the

shortest timeframe possible.”

www.cummins.com