Previous Page  18 / 52 Next Page
Information
Show Menu
Previous Page 18 / 52 Next Page
Page Background

16

MODERN MINING

March 2016

MINING News

First gold poured at Buckreef project in Tanzania

Tanzanian Royalty Exploration Corporation,

listed on the TSX and NYSE, reports that its

55 %-owned Buckreef redevelopment gold

project has successfully completed its first

gold pour.

The company notes that the timing

and amount of the pour of gold was not a

decision of management but was done in

response to a request made by the Deputy

Minister of Energy and Minerals of Tanzania.

“As a show of reasonable willingness to

cooperate on this non-contract item, we

did what we preferred not to do – pour

prematurely to proper market price,” says

Tanzanian Royalty. “It is the opinion of man-

agement that in time the gold price will rise

to at least US$800 higher than it was at the

time of the pour.”

The pilot CIC process plant is in the

process of being de-commissioned and

assimilated into a more flexible CIL process

plant designed with an initial throughput of

45 000 tonnes of mineralised material per

month.

The company is in the process of com-

pleting a Feasibility Study (FS) with a view

to targeting full-scale commercial gold pro-

duction in the second half of this year.

Celebrating the first gold pour at the Buckreef redevelopment gold project (photo: Tanzanian Royalty).

Reporting on its Yaramoko gold project in

Burkina Faso, Canada’s Roxgold Inc says

that approximately US$64 million of the

US$110,8 million capital estimate has been

spent to date and the project remains on

budget. The overall construction pro-

gramme is approximately 75 % complete

and on schedule and project commission-

ing remains on target for Q2 2016.

“We are very pleased with the progress

on the project in recent months,” com-

ments Roxgold’s President and CEO, John

Dorward. “With a number of important

infrastructure works now complete, the

team is focusing on underground devel-

opment and the start of commissioning

activities.”

During the month of December 2015,

the underground mine access infrastruc-

ture was completed with the Armtec

tunnel installed and the boxcut backfilled.

Underground development has

Yaramoko heads for second quarter commissioning

advanced well, with the underground

contractor, African Underground Mining

Services (AUMS), delivering several months

of above plan development rates. Total

development meterage stood at 1 237 m

as at the end of January against a planned

level of 972 m. The ramp had advanced

610 m from the portal and level develop-

ment was advancing on four levels, namely

the 5270, 5253, 5236 and 5219 levels.

Since the last update, the deposit has

been cross-cut at the above mentioned

four levels, exposing the 55 Zone vein.

Roxgold says it is encouraged by what

has been observed here with the orebody

and thickness consistent with that of the

block model. Initial chip sampling of the

crosscuts indicates that ore grades are also

consistent with expectations.

The vent raise contractor, Bauer Drilling,

is on site and has completed the pilings

for the first vent raise. Initial site works

for the raise boring contractor, Murray &

Roberts, are well advanced. All equipment

associated with the final installation of the

ventilation fans is on site.

Construction of the surface mine infra-

structure, including workshops, offices

and back-up power station, remain on

schedule. The surface settling ponds are

complete and the recycling of under-

ground water has commenced.

Construction of the processing plant

by the lump sum EPC contractor, the DRA/

Group Five Joint Venture, is approximately

80 % complete.

Since the last update, key mechani-

cal packages such as the thickener, kiln,

screens, cyclone pack, agitators, carbon

transfer pumps, reagent mixing and

crusher plant have been received on site

and installed.

The Carbon-in-Leach (CIL) tanks had

been erected to their full height by the

end of January with top of tank steel also

in place.

Pangolin Diamonds Corp, listed on the

TSX-V, has provided an update on its

Malatswae diamond project, located 105

km south-east of the Karowe diamond

mine of Lucara in Botswana.

The most recent results are from the

MTS grid where pyrope garnets with near-

source features were previously reported.

Following on these initial results, an addi-

tional 78 soil samples from the MTS grid

have been confirmed to contain kimberlite

indicator minerals.

Pyrope garnet has been visually-con-

firmed in 62 of the 78 grid samples and

ranges from 0,4-1,0 mm in maximum

dimension. Pyrope garnets with near-

source surface features are present in 55 of

the 62 samples, with 12 of those samples

having four or more garnets with near-

source features.

“These latest results continue to build

upon previous data for the MTS grid that

suggest that undiscovered kimberlites

are present within the MTS grid area,”

comments Pangolin’s President and Chief

Executive Officer, Dr Leon Daniels.

Pangolin updates

on Malatswae