Background Image
Previous Page  63 / 68 Next Page
Basic version Information
Show Menu
Previous Page 63 / 68 Next Page
Page Background www.read-tpi.com

October 2009 Tube Products International

61

after installation. One opening was made in the upper

area of the old pipe both in the starting construction pit

and in the destination construction pit. These openings

allowed the remaining water quantity that was unable to

be discharged by the existing drainage facilities to be

pumped off. High-pressure cleaning was then carried

out immediately, with simultaneous extraction and

transportation away of the sludge residue.

The solid incrustations left behind were removed by

mechanical cleaning. Calibration then provided a

‘surprise’ – unlike the specifications in all planning

documents, the old pipe in the repair section was not

DN 1,050, as assumed, but was only DN 1,000. In

order to able to use the PE 100 pipes already on site,

it was necessary to implement a more major reduction.

The technical parameters were recalculated. The high

flexibility of the Simona PE 100 pipe allowed the work to

continue within tolerance with no interruption.

Calibration with 985mm diameter followed by a

concluding camera inspection ensured that the old pipe

had been adequately prepared for the pull-in operation.

The counter-bearing structures required in the starting

construction pit and destination construction pit were

allowed for as early as digging the construction pits.

The swagelining process met all these requirements.

A great deal of positive experience with preceding

constructionprojects done by LudwigPfeiffer documents

the reliability of this repair process.

The swagelining process

The swagelining process is a cost-effective process

for the repair of discharge pipes comprising standard

PE 100 pipes without permanent annulus. It is one of

the reduction processes in accordance with DVGW

W 320. In the case of the swagelining process a long

pipe train comprising several Simona PE 100 pipes

is prefabricated on the construction site. The outer

diameter of the PE 100 pipe, at 1,060mm, is larger than

the inside diameter of the old pipe in order to guarantee

a durable Close-Fit position after installation.

The cross-section is reduced by tensile force and

compressive force for the duration of pipe pull-in. The

new pipe is pulled in with a pulling device on-site by a

reduction tool. The pipe remains constantly subject to

tensile stress during the pull-in process. Consequently,

it can be interrupted at any time, eg in order to connect

individual pipe trains before the pipe pull-in operation.

When the final position is reached, the tensile force

is reduced, thus increasing the outer diameter again.

The result is a perfect Close-Fit. The new Simona PE

100 pipe tightly follows the course of the old pipe. One

major advantage of this process is that time-intensive

preliminary work, such as cleaning the old pipe and

welding the individual pipe trains, can be carried out in

parallel in the construction process.

Preparatory measures

Various types of preparatory work were required so that

the new pipe could be easily pulled into the old pipe and

so that a Close-Fit position in the old pipe was reached

Figure 2

: Hot-tool butt welding is used to join the two pipe

trains tension-proof with one another

Figure 4

: The complete pipe train was pulled into the existing

pipe in a single pulling operation

Figure 3

: The 500m long pipe train was moved without difficulty

to the starting pit using lightweight equipment