Previous Page  33 / 48 Next Page
Information
Show Menu
Previous Page 33 / 48 Next Page
Page Background

Figure 18: Example of

tri-furcating termina-

tion into compact MV

switchgear.

Figure 19

is a good example of where things have gone wrong in the

past. The SF6 insulated ring main unit was installed with additional

metering, LV and protection Current Transformers (CTs). This often

happens and it is all because the wrong products were ordered, or

because end users have not understood the new technologies, or

wanted to stay with old technologies. We were able to locate this

problem before a failure accorded by using the EA Technologies

handle-held UltraTev Plus detectors. These tests are non-intrusive

and should be done on line. No interruptions of supply are required.

The installation should have been done with type 4 ter-

minations and single core XLPE cables. Instead a type 3

termination was installed and the CTs were installed

over the unscreened areas of the termination. This

installation would have failed if nothing had been

done. PD takes a long time to cause a failure in

terminations, but it is guaranteed to fail one day.

Testing to ensure reliability

Most end-users still use direct current (dc) cable pressure

test equipment, which gives no diagnostic results. This type

Figure 16: Example of screened and belted PILC cable termination

prepared from the top down principle.

Figure 17

clearly shows the extra base which needs to be supplied

with compact switchgear in order to ensure the correct three core

cable height is attained. This would not be the case for three single

core cables. The evolution of MV Power cables, switchgear and cable

accessories, has made it possible to considerably reduce the size

of cable boxes. The bending radius of three core cables has to be

considered and in the picture below special removable front covers

of the RMU and plinth have been designed to make the jointers life

easier. Implementing this will hopefully reduce jointer errors.

Figure 17: Example of SF6 RMU with an additional raising plinth and

removable front sections.

Figure 18

shows a clever way of terminating the core

XLPE MV power cables into small, compact switch-

gear. By performing a tri-furcating termination in

the duct or ground, three single core cables is

achieved. Terminating single core terminations

in such small cable boxes is recommended. This

small cable box has two cables terminated in it

and there is no risk that a failure could occur. Core

crossing is done under the cable box in the duct or

ground. Special attention should be paid to using the

right single cable clamps and gland plate material.

DRIVES, MOTORS + SWITCHGEAR

T AN FORMERS + SUBS ATIONS

Figure 19: Example of incorrect and correct termination into compact

MV switchgear with LV CTs.

According to

depth of lug

According to

depth of lug

31

April ‘17

Electricity+Control