Previous Page  71 / 84 Next Page
Information
Show Menu
Previous Page 71 / 84 Next Page
Page Background

January 2016

MODERN MINING

69

Top projects

COAL

innovation at

Shondoni

The massive winder house

was moved by crane across

58 m and hoisted to a height

of over 30 m before finally

being positioned on top of

the headgear.

technology to inject grouting via pipes inserted

down holes drilled in front of the work area,”

said Louw.

The shaft inclines at 12 degrees for a dis-

tance of 980 m, housing the 3,5 m/s single

incline conveyor that will extract 3 200 tons of

coal per hour.

Coal will be mined mainly from the 4-m

thick Number 4 seam at between 140 m and

160 m below surface, by normal bord-and-

pillar methods as employed at Middelbult.

Continuous miners break the coal and load

into shuttle cars, which deliver into feeder

breakers; an underground crusher sizes the

coal to -150 mm lump size. Section conveyers

take product onto trunk conveyors, which in

turn deposit it into underground bunkers; coal

reports to the incline conveyor from the main

underground bunker on Number 4 seam.

The 15 000-ton capacity surface bunker –

constructed by Stefanutti Stocks Civils – also

adopted an interesting approach by using pre-

cast ‘planks’ up to 20 tons in weight to facilitate

a safe and efficient construction process. Cast

in a dedicated precast yard nearby, the compo-

nents were placed sequentially by gantry crane

and stitched by concreting.

“This innovation led to a substantially safer

working environment, with much less need for

scaffolding and working at height during con-

struction,” said Louw.

The design went on to be commended at

the Concrete Society of Southern Africa’s

Fulton Awards 2015, where it was described

as an excellent example of hybrid or compos-

ite reinforced concrete structures – showing

the benefits of precast combined with in-situ

concrete.

Leading from the bunker is the record-

breaking, 21-km-long conveyor. It is reportedly

the longest in the world that can run this dis-

tance with drives only at the head and tail, an

achievement made possible by a more energy-

efficient drive system that reduces power

consumption.

“It must also curve to avoid a settlement and

a gold mine tailings dam and must cross roads

and waterways,” said Louw. “Environmental

concerns also demand that the belt is spill-free

and must be sealed when it crosses sensitive

areas.”

To minimise the environmental impact

of the conveyor, it was necessary to prevent

carry-back spillage along the conveyor route.

This was addressed by installing belt turn-

overs – at head and tail – to rotate the belt 180

degrees as it turned. This ensures that the dirty

side of the belt is facing up for both top and bot-

tom strands of the conveyor, stopping residual

material from falling off the belt as it passes

over idlers.

The conveyor is covered over its full length

to prevent rain from washing coal dust off the

belts, and to reduce the propagation of dust and

noise; dust suppression sprays at the transfer

chutes also help keep coal dust to a minimum.

The installed drive capacity on the conveyor

is a substantial 5 MW, with four drives at the

head and a single drive at the tail. An 80-ton

counterweight puts the necessary tension on

the belt to prevent slippage at either end. This

element of the project will be one of the last to

be finalised and will be commissioned in the

second half of 2016.

Maintenance and monitoring of this ambi-

tious conveyor design is clearly vital for smooth