Previous Page  10 / 60 Next Page
Information
Show Menu
Previous Page 10 / 60 Next Page
Page Background

8

MODERN MINING

July 2017

MINING News

ASX-listed Syrah Resources, which is

developing the Balama graphite project in

northern Mozambique, reports that over-

all construction progress completion was

90 % as at 30 June 2017. Processing plant

commissioning activities commenced in

May and continue as planned, including

energisation of the primary crusher sub-

station, and completion of function testing

for some material handling equipment.

The majority of supporting infrastruc-

ture for the plant site is complete, aside

from the water pipeline which is well

advanced. The main pipeline corridor has

been cleared and trenched (13,5 km) and

welding of the pipeline has begun.

Operational readiness for production

ramp up is also progressing well, says

Syrah, with most of the key operational

management, supervision and personnel

having been recruited and initial mine

development complete with stockpiling

of mineralised ore onto the ROM stock-

pile, ready for production. The laboratory

has been fully fitted out with state-of-the-

art equipment and is fully functional with

Bureau Veritas technical personnel already

mobilised to site. The laboratory is being

used in advance of production to train

personnel in processing and performing

ore characterisation work.

The project remains on schedule for

first production in August 2017 and the

project capital cost is US$193 million (plus

a project contingency of US$7 million).

Syrah says that the Mozambique

Minister for Mineral Resources and

Energy, Leticia Klemens, undertook a very

detailed visit to the Balama operation on

June 26. The visit focused on health and

safety, environmental compliance, the

Balama graphite project in the finishing straight

Looking south over the Balama site. This photo is fromMay this year (photo: Syrah Resources).

mine, processing plant and infrastructure,

the training and development systems

in place, and the high proportion of

Mozambican national employees, particu-

larly from the local communities.

The strong commitment Syrah has

already shown towards social responsibil-

ity in advance of production was noted,

and the Minister subsequently requested

that the company share the established

standards and processes with other

resources projects in Cabo Delgado prov-

ince and nationally.

The project has reserves of 114,5 Mt

at 16,6 % Total Graphitic Content (TGC)

(18,6 Mt contained graphite) and resources

of 1 191 Mt at 11,0 %TGC (128,5 Mt of con-

tained graphite), sufficient for a life of mine

of almost 60 years.

Balama will be a simple open-pit

operation with a low strip ratio. It will

employ a processing route consisting of

conventional processes including crush-

ing, grinding, flotation, filtration, drying,

screening and bagging. The plant will

produce a 95 % to >98 % TGC concentrate

across a range of flake sizes.

The processing rate is 2 Mt/a with the

nameplate capacity of the plant being

380 000 t/a of graphite concentrate. It

is envisaged that the operation will ini-

tially achieve a C1 production cash cost

of less than US$400 per tonne in the first

12 months, with this later reducing to less

than US$300 per tonne.

The flotation section of the Balama plant under construction (photo: Syrah Resources).