Previous Page  26 / 60 Next Page
Information
Show Menu
Previous Page 26 / 60 Next Page
Page Background

DIAMONDS

24

MODERN MINING

October 2016

A split shell design has been

adopted for the open pit.

a detailed two-year mine plan and schedule

was in place.

The Liqhobong property hosts two kimber-

lite pipes, a satellite pipe and the main pipe,

as well as associated blows and dykes, with the

cluster forming part of the Lemphane-Robert

kimberlite belt of northern Lesotho. The two

pipes were discovered in the 1950s but early

efforts to mine at Liqhobong were concentrated

on the 1,6 ha satellite pipe, which has a higher

grade but generally produced poorer quality

diamonds. European Diamonds built a plant

in 2005 to treat the satellite pipe ore and this

was later upgraded and expanded by Kopane

and Firestone. The upgraded facility – or pilot

plant, as it was known – operated from 2011 to

2013, treating ore from a trial mining campaign

conducted on the main pipe. The intention was

to generate some cashflow while the feasibil-

ity study on mining the main pipe was being

completed.

“Around 1,18 Mt was mined and this yielded

over 325 000 carats,” said Brown. “The plant

was, however, not really fit for purpose and the

trial mining exercise actually lost money. A

major problem was that the gap on the primary

crusher was less than 20 mm which resulted

in large stones being broken. We subsequently

did some reconstitution work on the broken

diamonds, analysing ten stones including one

of 74 carats. Our conclusion – and that of the

independent experts we con-

sulted – was that all the stones

were between 100 and 200 car-

ats when mined with two above

200 carats. So clearly there is a

potential for Liqhobong to pro-

duce large stones.”

The pilot plant has now been

dismantled and removed from

site and the new operation now

coming on stream is – to all

intents and purposes – a brand

new ‘greenfield’ mine. It will see

the 8,6 ha main pipe – which

contains a 23 Mct indicated and

inferred resource at a grade of 28

cpht – being mined to a depth of

383 m over a 15-year mine life at

a rate of 3,6 Mt/a – which will

result in 1 million carats a year

being produced.

The process plant is a twin-

stream (2 x 250 t/h) facility

which utilises a conventional

flowsheet comprising scrub-

bing, screening, three stages of

crushing, concentration via DMS

and final recovery using X-ray machines. The

settings on the crushing circuit are such that

any large stones in the 100-carat to 400-carat

range that are liberated by the scrubbers should

make it through to final recovery intact and

undamaged.

As regards the mining, a split shell design

has been adopted for the open pit, with a

14 m bench and 28 m double bench design.

Advantages of this approach include a reduced

risk of ramp failure (once two splits join then

a concentric ramp results), lower capex for the

initial mining fleet (due to lower waste strip-

ping) and less in-pit traffic congestion with

multiple ore and waste faces available. The

projected strip ratio is 2:1 over the life of mine.

In terms of carat production, Liqhobong will

be bigger than Gem Diamonds’ Letšeng, the

current flagship of Lesotho’s diamond mining

industry. Letšeng – which has an extremely low

grade of just under 2 cpht – produces approxi-

mately 100 000 carats a year, which is only a

tenth of Liqhobong’s projected production, but

is highly profitable because of the high quality

of its stones and its proven ability to produce

large diamonds on a regular basis. In 2015, it

received an average of US$2 299 per carat for

its production.

Liqhobong’s diamonds, by contrast, are only

expected to fetch an average price of US$165

per carat escalated over the life of mine. As