Background Image
Previous Page  35 / 68 Next Page
Basic version Information
Show Menu
Previous Page 35 / 68 Next Page
Page Background

developments

products &

www.read-tpi.com

July 2009 Tube Products International

33

and qualities of structural hollow steel

sections, both in its delivery and its

long-term performance. Twelve circular

hollow sections supplied by Corus Tubes

wind around the outside of the structure

to create the signature corkscrew-like

appearance, with the slender lines of the

curved steel tubes and the neat welded

joints ensuring the sharp lines of the

structure’s design could be achieved.

The elliptical structure provides an

enclosed crossing, which is fully glazed

with polycarbonate panels, ensuring

a safe and comfortable environment

for pedestrians and cyclists using the

bridge.

All the steel components were subject

to a rigorous testing regime, first by

Corus Tubes during manufacture of the

steel sections at its Corby mill, then by

SH Structures.

SH Structures, used to working on com-

plex tubular steelwork, pre-fabricated

the sections at the company’s facility.

As well as reducing the amount of work

that actually took place on-site, off-site

fabrication of the sections in the closed

factory environment meant work was

unhindered by prevailing bad weather

conditions that might have otherwise

caused delays on the exposed site.

The relatively low weight of the structural

steel components enabled sections to

be easily transported to the site, where

the only work required was the welding

of the splices to create the complete

90-metre span.

TimBurtonof SHStructures commented,

The complex design and fabrication of

the bridge meant that the footbridge

components needed to be carefully

pieced together – an intricate process

that was facilitated by the unique

properties of steel which allowed it

to be easily bent and shaped. This

enabled it to be designed to a range

of shapes that were easy to construct,

essentially giving the architect greater

design scope. In addition, the off-

site fabrication associated with steel

ensured that delivery of the project

incurred minimal disruption on the

locality through road closures – which in

itself created significant economic and

health and safety benefits.”

Raynesway Construction carried out the

complex operation to install the main

superstructure section of the footbridge

using one of the UK’s largest cranes,

complete with a 90-metre job and 600

tonnes of superlift counterweight.

The crane itself took a week to

assemble, having been delivered to site

in 45 separate loads. However, once

erected it was able to lift the 230 tonne

superstructure element of the footbridge

into position using a single operation

that commenced at 8.30pm.

Once the new bridge was successfully

located and secured into the support

structure, the lifting slings attaching the

bridge to the crane were removed and

the motorway was re-opened at 3am

the following morning – some three

hours earlier than planned – ensuring

that closure of the motorway was limited

to one evening.

Corus Tubes

– UK

www.corustubes.co.uk

The bridge was lifted into place in one

night