Southern Corridor GRIP 2017–2026 |
21
TSO PROJECTS
No. Project
TYNDP Code
Status
Commissioning
(TYNDP 2017)
TSO/Sponsor
1
Compressor station 1 at the
Croatian gas transmission system
TRA-F-334
FID PCI 6.26.3
2017*
2
LNG evacuation pipeline Omišalj -
Zlobin (Croatia)
TRA-N-090
Advanced Non-FID
PCI 6.5.1
2018*
3
Interconnection Croatia Slovenia
(Lučko-Zabok-Rogatec)
TRA-F-086
FID** PCI 6.26.1
2019
4
Interconnection Croatia -Bosnia
and Herzegovina (Slobodnica-
Bosanski Brod)
TRA-N-066
Advanced Non-FID 2019
5
LNG evacuation pipeline Zlobin-
Bosiljevo-Sisak-Kozarac
TRA-N-075
Advanced Non-FID
PCI 6.5.2
2020
6
Interconnection Croatia-Bosnia and
Herzegovina (South)
TRA-N-302
Advanced Non-FID 2021
7 Ionian Adriatic Pipeline
TRA-N-068
Advanced Non-FID 2022
8
Compressor stations 2 and 3 at the
Croatian gas tranmission system
TRA-N-1057
Non-FID
PCI 6.26.3
2020
9
Interconnection Croatia/Serbia
(Slobdnica-Sotin-Bačko Novo Selo)
TRA-N-070
Non-FID
2023
10
LNG Evacuation Pipeline Kozarac-
Slobodnica
TRA-N-1058
Non-FID
PCI 6.5.2
2023
11
Interconnection Croatia-Bosnia and
Herzegovina (west)
TRA-N-303
Non-FID
2026
12
Interconnection Croatia/Slovenia
(Umag-Koper)
TRA-N-336
Non-FID
2026
THIRD PARTY PROJECTS
No. Project
TYNDP Code
Status
Commissioning
(TYNDP 2017)
TSO/Sponsor
1 LNG terminal Krk
LNG-N-082
Non-FID
PCI 6.5.1
2018*
* Commissioning date has been updated to 2020
** This project has lost its FID status