Southern Corridor GRIP 2017–2026 |

21

TSO PROJECTS

No. Project

TYNDP Code

Status

Commissioning

(TYNDP 2017)

TSO/Sponsor

1

Compressor station 1 at the

Croatian gas transmission system

TRA-F-334

FID PCI 6.26.3

2017*

2

LNG evacuation pipeline Omišalj -

Zlobin (Croatia)

TRA-N-090

Advanced Non-FID

PCI 6.5.1

2018*

3

Interconnection Croatia Slovenia

(Lučko-Zabok-Rogatec)

TRA-F-086

FID** PCI 6.26.1

2019

4

Interconnection Croatia -Bosnia

and Herzegovina (Slobodnica-

Bosanski Brod)

TRA-N-066

Advanced Non-FID 2019

5

LNG evacuation pipeline Zlobin-

Bosiljevo-Sisak-Kozarac

TRA-N-075

Advanced Non-FID

PCI 6.5.2

2020

6

Interconnection Croatia-Bosnia and

Herzegovina (South)

TRA-N-302

Advanced Non-FID 2021

7 Ionian Adriatic Pipeline

TRA-N-068

Advanced Non-FID 2022

8

Compressor stations 2 and 3 at the

Croatian gas tranmission system

TRA-N-1057

Non-FID

PCI 6.26.3

2020

9

Interconnection Croatia/Serbia

(Slobdnica-Sotin-Bačko Novo Selo)

TRA-N-070

Non-FID

2023

10

LNG Evacuation Pipeline Kozarac-

Slobodnica

TRA-N-1058

Non-FID

PCI 6.5.2

2023

11

Interconnection Croatia-Bosnia and

Herzegovina (west)

TRA-N-303

Non-FID

2026

12

Interconnection Croatia/Slovenia

(Umag-Koper)

TRA-N-336

Non-FID

2026

THIRD PARTY PROJECTS

No. Project

TYNDP Code

Status

Commissioning

(TYNDP 2017)

TSO/Sponsor

1 LNG terminal Krk

LNG-N-082

Non-FID

PCI 6.5.1

2018*

* Commissioning date has been updated to 2020

** This project has lost its FID status