Background Image
Previous Page  15 / 76 Next Page
Information
Show Menu
Previous Page 15 / 76 Next Page
Page Background

May 2015

MODERN MINING

13

MINING News

Fill Dense, Abrasive, Clumped Material with these Ultra-Rugged Bulk Bag Fillers SOUTH AFRICA sales@flexicon.co.za +27 (0)41 453 1871 USA UK AUSTRALIA SINGAPORE CHILE +1 610 814 2400 +44 (0)1227 374710 +61 (0)7 3879 4180 +65 6778 9225 +56 2 2415 1286 DD-0565 Extreme-duty Bulk Bag Filler fed by Flexicon Flexible Screw Conveyor BLOCK-BUSTER™ Bulk Bag Conditioner and BULK-OUT™ Bulk Bag Discharger also offered by Flexicon Wide diameter fill head for loading of filter cake and irregular materials Purpose-built for ultra-heavy-duty mining applications, Flexicon bulk bag fillers handle filter cake, aggregates, abrasive minerals, dry chemical additives and other problematic materials that would choke or destroy general purpose fillers. Flexicon fillers range from simple, rugged, manual models to automated, high capacity models with pallet dispensers and heavy-duty drag chain pallet conveyors, weigh-filling one bulk bag per week to 20 per hour. Heavy-duty construction Mobile or stationary Manual or automatic Safety interlocked Interior or weatherproof Factory or on-site testing

DD-0565_FillDense_Layout 1 4/2/15 12:30 PM Page 1

Reporting on its organic growth projects in

its operating update for the quarter ended

31 March 2015, Sibanye Gold says the pre-

feasibility studies for the Kloof 4 Shaft and

Driefontein 5 Shaft below infrastructure

were completed in December 2014, both

delivering higher forecast returns than the

Group’s internal investment hurdle rates.

The projects have added approximately

1,1 Moz to the Driefontein and 0,5 Moz to

the Kloof gold mineral reserves.

Detailed feasibility studies for both

projects remain on schedule for comple-

tion during the June 2015 quarter and, due

to the favourable forecast returns, initial

preparatory project site preparation and

development commenced at Kloof 4 Shaft

in January, with the Driefontein 5 Shaft

project preparation planned to commence

in July.

Regarding the West Rand Tailing

Retreatment Project (WRTRP), Sibanye

says a detailed feasibility study consid-

ering a phased development approach

Sibanye updates on its organic growth projects

for the WRTRP was completed at the

end of the March 2015 quarter and is

currently undergoing an internal techni-

cal and financial review. This study has

incorporated the use of available surface

infrastructure to reduce upfront capital

and enhance value.

The infrastructure utilised includes

existing gold plants and elution capacity at

Driefontein and Kloof, as well as uranium

processing capacity at the Ezulwini metal-

lurgical complex.

Metallurgical test work undertaken

during the study has further enabled

refinements to the process design, result-

ing in reduced capital and operating costs.

The outcome of the study will be released

during the June 2015 quarter.

Sibanye now also owns the Burnstone

project near Balfour. Designed as a shallow

(~250 m to ~1 000 m), semi-mechanised

mine, Burnstone – on which construction

started in 2006 – produced approximately

38 000 oz of gold before being placed on

care and maintenance in mid-2012. It has a

complete metallurgical plant with a name-

plate capacity of 120 000 tpm.

Capital expenditure of R286 million was

approved in July 2014 for a 15-month con-

struction programme to complete critical

pumping infrastructure and re-align the

shaft steelwork, including the installation

of shaft service pipes and cables critical in

support of the mine build-up strategy. The

infrastructure project is on schedule for

completion by the end of September 2015

as originally planned and is forecast to be

completed within budget. The feasibility

study and development of the life of mine

plan is on schedule for completion in the

June quarter.

R150 million has been provisionally

approved to commence mine develop-

ment in 2015 with 2 000 m planned to be

developed into the initial targeted mining

areas by the end of 2015. During February,

the development commenced with a total

of 192 m completed for the quarter.