Background Image
Previous Page  25 / 76 Next Page
Information
Show Menu
Previous Page 25 / 76 Next Page
Page Background

COVER STORY

May 2015

MODERN MINING

23

extensive design and planning collaboration

between the teams to ensure that redesign dur-

ing manufacture and assembly was limited to

the bare minimum, thus avoiding time delays.

Barloworld Power committed to delivering

the first motivator to site a full two months

ahead of schedule so that it could be used to

move the first assembled rope shovel off the

assembly pad on the mine. This meant that the

unit had to be on site before the road embargo

on abnormal goods in Namibia, which was

effected on 3 December 2013. As the unit took

four days to get to site, the delivery schedule

was extremely tight.

Barloworld Power’s Customised Solution

Centre, together with the installation team,

pulled out all the stops to ensure that this hap-

pened and the unit was delivered to the Walvis

Bay branch of Barloworld Namibia on Friday

29 November 2013. The second motivator was

handed over on schedule by 31 January 2014.

Optimum design

The initial design of the unit incorporated all

the equipment and the engine in a single enclo-

sure, but during the detailed design phase this

proved to be impractical for several reasons:

the trailer became too cumbersome and

costly to manufacture;

the risk of fire damaging the electrical equip-

ment if it all shared a common enclosure

was deemed to be too great;

the risk of dust contamination on the electri-

cal equipment was too great;

the size of the generator meant that if this

solution was pursued, an 18 m long trailer

would be needed. This would have made

transport and movement of the unit on the

mine prohibitively difficult as well as being

very costly to build and maintain in the

long term;

the overall height of the unit on a standard

trailer would have resulted in an unaccept-

ably high centre of gravity, increasing the risk

of a rollover on a banked gradient.

With these issues in mind, it was decided

to design a step deck with a lower centre of

gravity and the generator mounted to it. The

electrical equipment enclosure with the fuel

tank is mounted separately on the gooseneck.

This proved to be the most successful arrange-

ment as it brought the centre of gravity down

by nearly 2 m and reduced the overall length

by 4 m, resulting in a unit that is stable and

relatively easy to manoeuvre.

The trailer has to be towed by a suitably

sized horse with a special low range gear-

box to successfully cope with the low speeds

needed to walk the rope shovel and negotiate

the gradients of an opencast mine. Owing to

the identical design of the trailers, two identi-

cal horses were needed.

A comprehensive fire detection and sup-

pression system was installed in the engine

compartment and a full detection system in the

electrical compartment.

The compact medium voltage switchgear

is also state-of-the-art, with IP 67 encapsu-

lated ingress protection of the environmentally

friendly vacuum switching contacts and the

MV conductors. This characteristic enables the

switchgear to be submerged in water for three

days without any negative effects on the main

conductors.

The durability of this section of the switchgear

was one of the main reasons for its selection as it

is highly suitable for a dusty desert environment.

The very low voltage control circuitry eliminates

potential hazards associated with dust or mois-

ture contamination. These design measures do

not mean the equipment is maintenance free and

a strict maintenance schedule is in place.

A motivator moves a

Cat 7495 electric rope

shovel.

Barloworld Power

committed to

delivering the first

motivator to site

a full two months

ahead of schedule

so that it could be

used to move the

first assembled

rope shovel off

the assembly pad

on the mine.