Table of Contents Table of Contents
Previous Page  20 / 386 Next Page
Information
Show Menu
Previous Page 20 / 386 Next Page
Page Background

RISK FACTORS

04

4.3 Legal risks

4.3.2.6.

EARLY TERMINATION CLAUSES

The group enters into contracts which sometimes include clauses allowing the

customer to terminate the contract or reject the equipment if contract clauses

concerning schedule or performance have not been met. Difficulties concerning

products and services provided under this type of contract could thus result in

unexpected costs.

In addition to the above-mentioned negative financial consequences, contract

performance difficulties could harm the group’s reputation with existing or potential

customers, particularly in the nuclear sector.

4.3.2.7.

REQUIREMENTS CONTRACTS

Some contracts signed by entities of the group, in particular in the Chemistry-

Enrichment Business Unit, are for variable quantities, depending on our customers’

reactor requirements. These are known as “requirements contracts”.

The estimates provided by AREVA’s customers in connection with these contracts

may therefore be revised downwards in certain circumstances, with a corresponding

reduction in the revenue anticipated by AREVA for the contracts in question.

4.3.3.

RISKS AND DISPUTES INVOLVING AREVA

AREVA is exposed to the risk of disputes that could lead to civil and/or criminal

penalties. AREVA cannot guarantee that it is not potentially exposed to claims or

investigations that could have a significant unfavorable impact on the group’s image

and financial performance.

4.3.3.1.

OLKILUOTO 3 EPR POWER PLANT (OL3)

On December 5, 2008, the AREVA-Siemens consortium initiated arbitration

proceedings with the International Court of Arbitration (ICC) for delays and

disruptions suffered in connection with contract performance and for the resulting

additional costs incurred (“D&D Claim”). In July 2012, the court of arbitration

rendered a final partial decision enjoining TVO to release 100 million euros plus

interest due to the AREVA-Siemens consortium and withheld in contravention of

the contractual provisions. That decision was duly executed by TVO.

As of the end of 2016, on the legal level, the pre-trial investigation phase of the

legal proceeding begun in 2008 between the AREVA-Siemens consortium and

TVO continues. The AREVA-Siemens consortium continues to exercise its rights

in connection with the arbitration proceedings.

The consortium’s claim for compensation for damages concerns a total amount

of 3.5 billion euros. TVO’s claim against the consortium amounts to approximately

2.3 billion euros.

In accordance with the schedule of the arbitration proceeding, a partial decision was

rendered by the court on November 7, 2016. While that decision allows some of

TVO’s claims, it does not necessarily constitute a decision on the financial outcome

of the dispute between the parties. Other intermediate decisions are expected before

the final decision, not expected before the end of 2017 or early 2018.

In addition, the consortium and its counsel still believe that the allegations of

intentional gross negligence set out by TVO in its claim against the consortium

remain unjustified.

Concerning the OL3 project, the reader is invited to peruse the detailed information

given in note 24.

Provisions for losses at completion

of Section 20.2.

Notes to the

consolidated financial statements

of this Reference Document.

4.3.3.2.

RISKS OF DISPUTES RELATED TO ANOMALIES

IDENTIFIED IN THE MANUFACTURING PROCESS

OF CERTAIN COMPONENT FORGINGS AT CREUSOT

Following the announcement in late April that documentary anomalies had been

found in the follow-up of equipment manufacturing processes at the Creusot plant,

an audit is currently being conducted of all of the manufacturing files.

In October 2016, Greenpeace and other associations filed a complaint against

EDF and AREVA with the public prosecutor’s office of the High Court of Paris

concerning these anomalies, in particular those affecting a steam generator of

Fessenheim unit 2.

In addition, in October 2016, pursuant to article 40 of the French Code of Criminal

Procedure under which any established authority and any publicly appointed official

or civil servant with knowledge of a felony or a misdemeanor within the framework

of his/her functions is required to “advise the State Prosecutor without delay”, the

Chairman of ASN referred the matter of “irregularities” in the part manufacturing

files at AREVA NP’s Creusot plant to the State Prosecutor. According to a judicial

source, a preliminary investigation has been opened by the public health section

of the public prosecutor’s office of Paris pursuant to this referral.

To date, the analyses have found that no reported anomaly compromises the

mechanical integrity of the parts concerned. Additional tests and analyses are in

progress, in particular on an equipment item delivered to the Fessenheim 2 power

plant, in order to respond to requests from the nuclear safety authority ASN following

the suspension of the test certificate of one of the steam generators.

A more extensive analysis of the manufacturing files (unmarked files) is in progress

and concerns more than 6,000 files. Additional identified anomalies are being dealt

with in the same way. In this regard, an anomaly on a steam generator delivered to

the Flamanville 3 site was the subject of characterization for purposes of responding

to requests from the safety authority. This situation could result in other civil or penal

implications, both in France and abroad.

Concerning the anomalies identified at le Creusot and related subjects, the reader

is invited to also peruse the detailed information given in Section 9.1.

Overview

and in note1 of Section 20.2.

Notes to the consolidated financial statements

of this

Reference Document.

4.3.3.3.

URAMIN ACQUISITION

Following the preliminary inquiry led by the French national financial prosecutor’s

office, two judicial inquiries against persons unknown were opened concerning

the conditions of the acquisition of UraMin on the one hand, and the presentation

of the company’s financial statements from 2009 to 2012 relative to this purchase

on the other hand.

In response to the subpoena received from the court in December 2015, AREVA

brought an independent action for damages in connection with the investigation

of the UraMin acquisition.

20

2016 AREVA

REFERENCE DOCUMENT