BUSINESS OVERVIEW
06
6.4 Operations
the French nuclear safety authority ASN. On December 12, 2015, ASN validated
the test programproposed by AREVA concerning the bottom head and the closure
head of the Flamanville 3 reactor vessel. That program aims to demonstrate the
mechanical properties of those parts in connection with the fitness for service
report required by ASN.
The test program was launched in late 2015 and ended on December 7, 2016.
Tests were carried out on vessel bottom heads and closure heads analogous to
those of the Flamanville 3 EPR reactor. The toughness properties measured in
sacrificial parts meet the expectations of ASN’s follow-up letter of December 2015;
they are in the high end of the range of what was anticipated by AREVA’s experts.
An independent, external organization was chosen by EDF and ASN to monitor
these tests. All three of them were therefore associated in the program of analysis.
New Build projects
SOUTH AFRICA
The South African government is currently in the process of revising its energy
plan to 2050. A public debate has been opened and will run until February 2017.
The project will be consolidated after this debate and submitted to the Council of
Ministers for a decision, with promulgation of the plan not expected to occur before
April 2017. In fact, the base scenario postpones the startup of nuclear power as
from2037 andmaintains the long-term target of 20GWof nuclear electricity. AREVA
will participate as a member of the French team. The South African government
is supposed to send the call for proposals to the governments of countries whose
technology corresponds to South Africa’s requirements.
SAUDI ARABIA
Saudi Arabia plans to build several sets of reactors for generating capacity of
17.6 GWe by 2040. In June of 2015, the Ministry of Foreign Affairs and the King
Abdullah City for Atomic and Renewable Energy (KACARE) signed a letter of intent
to launch a feasibility study for the construction of two EPR reactors in Saudi Arabia.
The next stage will be to create a regulatory authority and a legal framework for the
construction and operation of nuclear reactors in Saudi Arabia, with the cooperation
of the Finnish nuclear safety authority STUK, which has been appointed to provide
support to KACARE.
INDIA
In 2015, AREVA signed a contract with NPCIL for pre-engineering studies on
the Jaitapur EPR project and a Memorandum of Understanding (MOU) with
the engineering company Larsen & Toubro to examine areas for cooperation in
connection with the project. Both of those activities are advancing according to plan.
The objective is to continue preparations for certification of the EPR reactor in India
by the Indian safety authority and to finalize the project’s financial and economic
conditions in particular as well as its technical specifications. EDF has now taken
leadership for the industry.
POLAND
Poland wishes to include nuclear power in its energy mix and is considering
the installation of 6 GWe of nuclear generating capacity by 2035. The choice of
technology could be made in 2018.
A new government was formed in Poland in October 2015. PGE started the
environmental impact study process in November. AREVA worked with EDF to
plan for a possible call for proposals and attended different seminars, for which
they signed a “Statement of Participation”.
CZECH REPUBLIC
OnMay 18, 2015, the government of the Czech Republic approved the new version
of the country’s Energy Policy for the next 25 years.
This document includes the “National Action Plan for the Development of Nuclear
Energy in the Czech Republic”, which calls for the finalization of the construction
of additional nuclear units aimed at producing 20 TWh of power by 2035; lifecycle
extension of four units of the Dukovany power plant (raising it from 50 years to
60 years); and, gradually, the possible construction of additional units to replace
that power plant.
With support fromAREVA, EDF responded to a Request for Information (RFI) issued
by the Czech Ministry of Industry and Trade. The RFI concerns two units, one at
the Dukovany site and the other at the Temelin site.
UNITED KINGDOM – HINKLEY POINT C
At the end of September 2016, AREVA signed contracts with EDF and Nuclear
New Build Generation Company (NNB), a joint venture between the EDF group
and the Chinese group China General Nuclear Corporation (CGNC), which define
the basis for its work on the project.
AREVA was awarded several subcontracts for this project.
AREVA NP will be in charge of:
p
the delivery of two nuclear steam supply systems (NSSS), including their design,
procurement and startup;
p
the execution and supply of the power plant’s operational and safety
instrumentation and control system;
p
the fabrication of the fuel needed to operate the two NSSS.
AREVA will supply the necessary materials for fuel fabrication by producing the
uranium and providing conversion and enrichment services.
Execution of these contracts began in early January 2017 following the fulfillment
of all of the preconditions.
The transformation of the French nuclear industry decided by the French State
in 2015 could have an impact on the distribution of the scope of supply.
TURKEY – SINOP PROJECT
In September 2016, AREVA NP signed a preliminary engineering contract withMHI
to support the technical and cost feasibility study for the proposed construction and
operation of four ATMEA1 reactors at the Sinop site in Turkey.
The ATMEA company signed a license agreement making the ATMEA1 technology
available to MHI and AREVA NP for purposes of this feasibility study.
Human and industrial resources
The Large Projects Business Unit’s teams are located in France, Germany, Finland
and China.
Relations with customers and suppliers
The Large Projects Business Unit’s customers are utilities from all over the world,
including both well-established companies and newcomers to the market.
The entity offers reactor solutions that are synergistic with the group’s other
operations, such as the Component Business Unit, the Fuel Business Unit and the
Installed Base Business Unit.
2016 AREVA
REFERENCE DOCUMENT
85