Previous Page  32 / 64 Next Page
Information
Show Menu
Previous Page 32 / 64 Next Page
Page Background

CONSTRUCTION WORLD

MARCH

2017

30

PROJECTS & CONTRACTS

AMD poses a major environmental threat on the Witwatersrand.

The depletion of gold reserves in the area has meant a cessation

of mining activities and related dewatering operations, which has

resulted in the flooding of mining voids. AMD is generated when ore

and other sulphide-containing mining waste is exposed to oxygen

and water. The water in the mining voids thus becomes acidic and

contaminated with heavy metals.

TCTA was mandated by the Department of Water Affairs to

implement the necessary AMD water management and treatment

infrastructure. The project encompassed treatment plants in the

Randfontein Estates area (Western Basin), the ERPM South-West

Vertical Shaft area (Central Basin) and the Grootvlei Mine Shaft

No. 3 area in Springs (Eastern Basin).

The Eastern Basin plant designed by AECOM (in association

with Golder Associates) followed typical industry practice for

water/wastewater treatment works, says Claire Hurrell, senior civil

engineer, Africa for AECOM. “Some aspects of the detailed design

were verified and optimised using state-of-the-art techniques, which

not only added value to the engineering, but also ensured cost-

savings for the client.”

Hurrell explains that, due to the size of the project, AECOM

decided to standardise on tried-and-tested technology, as this

has been proven to work best globally. “However, we were able to

improve on the standard abstraction method.”

The three 20-m-long by 1-m-diameter super duplex stainless steel

deep-level abstraction pumps selected were installed from ground

level down into the 370-m-deep shaft, allowing for the abstraction of

the AMD without having to re-establish underground workings.

Construction began in June 2014, and was completed in August

2016. The total construction cost was just under R1-billion. The

main contractor was the CMC/PG Mavundla Eastern Basin Joint

Venture, with Andritz supplying the deep-level abstraction pumps.

Prior to construction, an underwater camera was lowered into the

flooded mine shaft at the Eastern Basin to check for any blockages

or significant damage to the shaft. A modified underwater sonar

system was also deployed to provide a wider field of view in order to

reduce the potential risk of damage to the abstraction pumps.

Such preliminary investigation was essential as the mine

shaft had been in disuse for several years, and had seen a lack

of maintenance, as well as vandalism by illegal miners. Properly

equipped and experienced professional mining rescue teams

removed debris and cleared any obstacles from the mine shaft.

Additional constraints were posed by a railway on one side

and a wetland on the other. Therefore the plant design allowed

for the deep excavations for the thickener recycle pump station

to be moved as far as possible out of the wetland area for ease

of construction.

However, these excavations still posed a considerable construction

challenge, as the excavated material was silty clay prone to shear

failures. Hence extreme care had to be taken during excavation.

“A decision was taken to use self-drilling anchors, which flush

the area with grout while drilling takes place. This allows the hole to

remain open while the voids are being grouted and stabilised in the

same operation,” Hurrell highlights. “The solution was implemented

successfully, allowing for the necessary lateral support to be

installed in the large thickener excavations.”

Environmental considerations were also paramount on this

project. It was essential to adhere to the programme dates to

avoid AMD rising in the mining void, and reaching a point where it

threatened to pollute natural aquifers and decant at surface.

The plant, which has been operating successfully since August

2016, is reducing the AMD level in the mine shaft by significantly

reducing the iron and manganese levels and increasing the pH to an

acceptable level for discharge into the environment.

Hurrell indicates this project signifies AECOM’s commitment

to balancing not only South Africa’s, but the world’s, need for

safe, reliable water, while protecting this critical natural resource.

“Combining our knowledge of local African markets with a global

network of creative engineering and technical expertise, our

sustainable, multi-disciplinary approach to water engineering

produces high-quality, cost-effective, energy-efficient, functional

and visionary solutions.”

In fact, AECOM has water professionals who work in and across

the major markets of drinking water, wastewater and conveyance

to deliver comprehensive solutions to safeguard human health

and the environment. Worldwide, including Africa, AECOM designs,

builds, finances, operates, and manages projects and programmes

that unlock opportunities, protects the environment and improves

people’s lives.

The company works with clients across the entire project

lifecycle – from initial planning studies through final construction

and operations and maintenance services – on both traditional

and alternative project-delivery options (design-build, public-private

partnerships, and financing).

COMMENDATION FOR WORK

on AMD treatment plant

AECOM received a ‘Highly Commended’ award at

Construction World’s

Best Projects Awards 2016 for

work on the Eastern Basin Acid Mine Drainage (AMD)

treatment plant on behalf of the Trans-Caledon

Tunnel Authority (TCTA). This is one of the largest

high-density sludge (HDS) plants in the world, with a

maximum treatment capacity of 110 M

/d.

“A decision was taken to use self-drilling anchors, which

flush the area with grout while drilling takes place.”