Previous Page  39 / 64 Next Page
Information
Show Menu
Previous Page 39 / 64 Next Page
Page Background

June 2016

MODERN MINING

37

WEST AFRICA

feature

Pit design. The pit will

eventually be approximately

3 km long and 500 mwide

with a maximum depth

of around 80 m. Nordgold

will undertake the mining

in-house.

Bouly has been designed as

a heap leach project. The

agglomeration drum is

seen here.

US$10 million less than initial capex guidance

of US$155 million due to significant savings

achieved during earthworks conducted in-

house and lower equipment prices combined

with disciplined procurement and foreign

exchange gains.

All major mechanical equipment, plate work

and structural steel have been installed with

piping and electrical installation progressing

on schedule. The entire mining fleet had been

delivered to site and was commissioned by the

end of Q1 2016. Pre-stripping of the starter pit

began in late February 2016 and the first ore

was mined in March. Approximately 76 % of

earthworks on the heap leach pad and 56 %

of the pad HDPE lining were completed by the

end of Q1 2016.

Nordgold produced 950 000 ounces of gold

in 2015. Its portfolio of mines includes three

in Africa – Taparko and Bissa in Burkina Faso

and Lefa in Guinea – with the balance being

in Russia and Khazakstan. Nordgold was

established in 2007 as Severstal Gold, a gold

producing subsidiary of Severstal, the Russian

steel company owned by Alexey Mordashov.

The proximity of Bouly to Bissa means that

the two mines will be able to share infrastruc-

ture. Commissioned in early 2013, Bissa is an

open-pit/CIL mine which is expected to pro-

duce 200 00 ounces of gold in 2016. Nordgold’s

other operating mine in Burkina Faso, Taparko,

also an open-pit/CIL operation, is located

200 km north-east of Ougadougou. It produced

approximately 83 000 ounces of gold in 2015.

Nordgold’s third African mine, Lefa in Guinea,

is similar in size to Bissa in terms of gold pro-

duction (214 000 ounces in 2015). Opened in

2008 and acquired by Nordgold in 2010, it is

a typical open-pit mine with processing via a

CIP plant.

Photos courtesy of Nordgold