22
CONSTRUCTION WORLD
JANUARY
2016
PROJECTS AND CONTRACTS
Many other firms – especially in the
geotechnical field where the logis-
tics of housing teams of people
and moving massive, special-
ised machinery in remote and challenging
conditions – have failed where Franki has
been unusually successful. The stories of the
latest contracts in Swaziland are examples
of this success and also demonstrate the
power of the Franki pile and of being part of
the Keller group.
Ninety-two thousand, five hundred
and seventy-two. That’s the total non-LTI
(Lost Time Incident) man hours worked
on the four Frankipile Swaziland contracts
that commenced in October 2014. The
human resources included a total of 74 local
labourers, who were employed on all the
contracts. The equipment included six Franki
piling rigs, three piling cranes, a service crane
and seven auger rigs.
Frankipile Swaziland submitted four
tenders in 2014, all of which were for the design
and construction of piled foundations. These
tenders were based on Pre-Drilled Driven
Cast-In-Situ piles (Franki piles), whereas the
competitors selected the Continuous Flight
Augur (CFA)-type pile.
Two of the tenders submitted were to
the Swaziland Ministry of Economic Planning
– one for the new International Conference
Centre (ICC) and the other for a new Five Star
Hotel (FISH) in Ezulwini. According to Franki
project manager, Devendra Lalbasanth, the
tenders submitted for both contracts incorpo-
rated the Franki pile as opposed to the CFA pile
alternatives submitted by competitors.
“These high profile contracts required low-risk
technical solutions,” says Lalbasanth, “and the
Franki pile provided the guarantees that were
sought by the professional team.”
International Conference
Centre
Of concern to most of the professional team
was Frankipile Swaziland’s ability to adhere
to the contractual programmes, should both
contracts be simultaneously awarded to them.
“We managed to allay these fears by stressing
the power of the backing of the greater Keller/
Franki Africa group, should additional resources
have been required,” Lalbasanth says.
As these contracts were to be undertaken
under the new Swaziland Construction Regu-
lations which stipulate that a Joint Venture
with a local construction company was
required, Frankipile Swaziland teamed up with
Roots Civils on both contracts.
The piling contract for the ICC called
for the installation of 1 562 No. Franki piles.
“One of the challenges encountered on this
project was the presence of boulders and
although this was highlighted during the bid
clarification, the actual quantity and extent
of the boulder formation were unexpected.
This complication was resolved through the
removal of near-surface boulders, coring
through the boulders with a Casagrande B180
piling rig, founding the pile on large boulders
or spanning the boulders in consultation with
the structural engineer,” says Lalbasanth.
The work was completed in May 2015 and
a working pile load test, which was under-
taken in the area where the soils were deemed
the poorest across the entire site, produced
highly favourable results. Pile Echo Testing
(PET) tests are being undertaken on every pile
as the main contractor excavates and correctly
trims each pile.
Five star hotel
Piling to the FISH Contract, which comprised
the installation of 1 016 No. Franki piles, was
completed in April this year. The conditions on
the FISH site were more favourable than those
encountered on the ICC site with a working
pile load test producing very favourable
results. The structural engineer appointed a
representative on site who monitored quality
and progress on a daily basis and Franki
continuously received positive feedback from
them on its performance including its adher-
ence to the stringent safety protocol. In addi-
tion, an external safety audit praised Franki’s
achievements in no uncertain terms which,
according to Lalbasanth, is testament to the
attitude and commitment of the site manage-
ment towards the safety and well-being of all
who were involved.
The other two jobs were for, firstly, the
Hlane bridge, which was awarded to Franki
by Inyatsi Construction in February 2015. This
project commenced in late March 2015 and
was completed within two weeks.
Secondly the MVA Head Office, in
Mbabane, where Franki was the lowest at
tender stage and, after further value engi-
neering, the client appointed Franki as the
piling subcontractor to Stefanutti Stocks. The
scope of works was to install a total of 252 No.
Franki piles of which 80% were tested using
the PET method. A working pile test was also
carried out and the results were well within the
acceptable criteria. This contract was success-
fully completed in early December 2014.
The Franki pile
The successful completion of work in Swazi-
SWAZI
CONTRACTS SHOW
company’s mettle
For years Franki Africa has shown its prowess in working
in Africa whether in the surrounding SADC region or even
further afield in countries tens of thousands of kilometres
from Franki’s base in Johannesburg, South Africa.
>
The site for the new international hotel and conference centre site in Ezulwini, Swaziland.




