Previous Page  18 / 56 Next Page
Information
Show Menu
Previous Page 18 / 56 Next Page
Page Background

16

MODERN MINING

November 2016

MINING News

In its report for the quarter ending

30 September 2016, ASX-listed Syrah

Resources says that its Balama graphite

project remains on course for commission-

ing in Q2 of calendar year 2017.

Balama – situated in the Cabo Delgado

province of northern Mozambique, some

200 km west of the port town of Pemba –

currently hosts what is reported to be the

world’s largest reserve of contained graph-

ite at Balama East and Balama West, with

a combined ore reserve (JORC 2012) of

81,4Mt at 16% total graphitic carbon (TGC),

sufficient for over 40 years of mine life.

The project is planned as a simple, open-

pit mining operation with a low strip ratio.

Based on a mining feed rate of 2 Mt/a, at an

average head grade of approximately 19 %

TGC over the first 10 years of operations,

approximately 355 000 tonnes of graphite

Golden Star awarded mining lease for Mampon

Golden Star Resources (GSR), listed on the

NYSE MKT and TSX, has received a mining

lease for the Mampon deposit in Ghana.

Mampon is a high grade, oxide deposit

containing 45 000 ounces of gold (304 kt at

4,60 g/t), approximately 80 km to the north

of GSR’s CIL processing plant at the Bogoso

site. There is an existing, good quality road

connecting the deposit and the processing

plant for the majority of the distance, so lim-

ited capital expenditures will be required in

order to bring Mampon into production.

Higher grade ore from Mampon will be

blended with ore from the Prestea Open

Pits, which is expected to enhance Golden

Star’s cash flow in 2017. Following the

receipt of the mining lease, the next step

for the company is to obtain an environ-

mental permit. GSR expects to start mining

Mampon in the first half of 2017.

Golden Star began mining the Prestea

Open Pits in the third quarter of 2015 to

bridge the gap between the Bogoso refrac-

tory operations ceasing production and

the commencement of production from

the high grade Prestea Underground Gold

Mine, which is expected to occur in the sec-

ond quarter of 2017.

The company had anticipated that pro-

duction from the Prestea Open Pits would

be completed by the end of the third quar-

ter of 2016 but production is now forecast

to continue until the second half of 2017.

Golden Star says it will also endeavour to

delineate additional mineral reserves in the

area in order to further extend production

from the Prestea Open Pits and maintain a

second ore source from the mine.

“I am very pleased that Golden Star has

been granted themining lease for Mampon,”

comments Sam Coetzer, Golden Star’s

President and CEO. “Through mining this

high grade surface deposit we will generate

strong short-term cash flow and it will assist

us in maintaining production from Prestea

until Prestea Underground commences pro-

duction in the second quarter of 2017.

“With exceptionally high grade min-

eral reserves at 14,02 g/t, the real prize at

Prestea is the underground mine, but the

Prestea Open Pits have provided and will

continue to provide useful cash flow to us

during this transition period and I am very

glad that, along with Mampon, they will

now continue to produce until at least the

second half of 2017.”

concentrate will be produced per annum.

Syrah intends to move product from

Balama to Nacala port, located approxi-

mately 490 km south-east of the project.

Trucking of product will be outsourced to

a contractor and, at full production, there

will approximately 67 trucks (B-Double

trailers), each transporting approximately

36 one-ton bags of product from Balama

to Nacala daily.

The ramp up of personnel on site has

continued with approximately 1 400 direct

staff and contractors on site by late October,

a figure which is expected to peak at 2 000.

Detailed engineering and design of the

process plant has been completed and

over 70 % of the required concrete for the

plant has been poured by the civil contrac-

tor, CMC Africa.

The mining fleet required for full opera-

Balama on course for Q2 2017 commissioning

Slabs for the product classification and bagging area at Balama (photo: Syrah).

tions has beenmobilised including nine Bell

B40 articulated dump trucks, two Liebherr

excavators, two Caterpillar dozers, two

Caterpillar graders and two fuel tankers. The

mining contractor, Tayanna Mozambique,

has commenced establishment of its min-

ing compound and offices. Construction of

the run-of-mine (ROM) pad with a capacity

of 360 000 tonnes is underway with com-

pletion expected in January 2017.

The Structural, Mechanical and Piping

(SMP) contract has been awarded to Kentz

Engineers & Contractors Limitada (Kentz), a

member of the global SNC-Lavalin Group.

Kentz has mobilised to site and established

a 300-person camp.

Syrah reports that the Balama project

budget has been increased from US$175

million to US$185 million to incorporate

changes of scope related to improved

product quality. These changes are: intro-

duction of attrition cells to the process flow

sheet; and additional on-stream analysis to

optimise product qualification.

During the quarter, Syrah announced

the resignation of MD Tolga Kumova as

“part of a transition reflecting the evolving

strategic direction of the company and the

key development activities it is currently

undertaking”. Chairman Jim Askew has

stepped into an Executive Chairman role for

the interim period and, says Syrah, a global

search for a new MD has commenced with

the objective of making this appointment

within the next fewmonths.