Previous Page  24 / 56 Next Page
Information
Show Menu
Previous Page 24 / 56 Next Page
Page Background

COVER STORY

22

MODERN MINING

November 2016

now largely complete. In addition, the project

involves the upgrading of the ventilation infra-

structures; improvement and modernisation of

the underground ore handling infrastructure to

facilitate ore flow, storage and sorting efficiency;

upgrades to the Nchwaning II surface plant

infrastructure (not in WorleyParsons’ scope);

and the reinstatement of the Nchwaning I mine.

In Greyling’s view, one of the highlights of

the BRP has been the sinking of the new 5,5 m

diameter, 167 m deep, concrete-lined ventila-

tion shaft at Gloria. “The main challenge was

that the sinking had to take place through

Kalahari sand, as well as calcite, red clay and

conglomerate before the shaft entered the

more competent tillite formations,” he notes.

“Because of the Kalahari sand, we introduced

perimeter piling to a depth of 35 m. In addi-

tion, dewatering holes and cementation of the

areas just above the clay formations reduced

the influx of water into the shaft and prevented

excess disturbance of the clay during the sink-

ing process.”

The sinking was delayed slightly in the slow

sink phase due to the soft ground conditions.

To mitigate the time lost, the contractor agreed

to implement a continuous operations cycle

during the main sink phase until completion of

the station cutting.

Additional precautions were taken to pre-

vent any delays while sinking through the clay

formations. During this process it was impor-

tant to keep the lining as close to the shaft

floor as possible to minimise contact with air

and moisture. Any stoppage – due to a Section

54 notice, for example, being applied to the

mine – would have had severe consequences.

Fortunately, the sinking portion of the project

was completed without incident.

Once the shaft entered the competent tillite

formations, normal sinking took place (from a

depth of 71 m to 167 m). The sinking stage was

designed to accommodate ‘Hong Kong’ drills.

This methodology reduced the need for people

on the shaft bottom.

Cleaning was carried out using an excavator.

Corrugated steel rings were used for temporary

support in the shaft and the cycle ensured that

the lining was never more than 4 m from the

shaft floor.

The contractor, Murray & Roberts Cemen­

tation, worked for more than a full year (400

days) without a lost time injury. “Taking into

account the high risk nature of the work it per-

formed, this was an excellent achievement,”

comments Greyling. He adds that prior to

sinking Gloria, Murray & Roberts Cementation

had worked on another shaft of similar dimen-

sions in the Kalahari Manganese Field (KMF),

and thus had some experience of the difficult

ground conditions characteristic of the area.

Greyling points out that the successful com-

pletion of the shaft reinforces the reputation of

WorleyParsons as a world leader in the design

and implementation of shaft projects. He adds

that WorleyParsons RSA has been the EPCM

contractor on the majority of shafts under-

taken in South Africa in recent years. These

have included Impala 17 Shaft, as well as the

shafts at the Styldrift and Bakubung platinum

mines and the Shondoni coal project. A current

flagship contract is the Venetia Underground

Project (VUP), where WorleyParsons RSA is

providing engineering consulting services that

include detailed engineering, execution and

support in procurement and construction man-

agement. The VUP, which probably ranks as the

single biggest mining project currently under-

way in South Africa, includes the sinking of two

vertical shafts to depths of just over a kilometre.

Turning to the work at the Nchwaning

mines, Greyling says a relatively early achieve-

ment was the completion in September 2014 of

Nchwaning II shaft feed

conveyor drive and take-up

arrangements.