Previous Page  25 / 56 Next Page
Information
Show Menu
Previous Page 25 / 56 Next Page
Page Background

COVER STORY

November 2016

MODERN MINING

23

a ventilation fan installation at Nchwaning III

shaft. The 460 kW centrifugal fan was installed

adjacent to the existing three fans. The

change-over of the surface fan intake from the

trifurcated inlet to a quadfurcated inlet was

successfully accomplished and the existing

fans returned to service as planned.

At Nchwaning II, the vertical shaft upgrade

has comprised refurbishment of the exist-

ing shaft steelwork, installation of new shaft

loading facilities and the replacement of the

existing 8-ton skips with new 14-ton skips. A

refurbished rock winder has also been installed

adjacent to the existing winder while the exist-

ing man winder was also upgraded. Also

required have been headgear and sheave altera-

tions to suit the new ropes, larger skips and

winder placement.

All design work pre-construction and engi-

neering support during the shaft upgrade was

done by WorleyParsons, with Assmang taking

direct charge of construction activities under

Hennie Wessels from Assmang.

The Gloria shaft stripping and second escape

package, together with the Nchwaning II head-

gear and shaft upgrade, were combined and

Group Five was awarded the contract in April

2015. Stefanutti Stocks Civils was contracted

to construct the winder house and Winder

Controls installed the winder.

Refurbishment of the Vecor rock winder

(to be used at Nchwaning ll shaft) was com-

pleted in June 2015 and the winder house in

August 2015.

A portion of the refurbishment of the shaft

steel work was carried out over weekends so

as not to interrupt mining activities. The major

work, which includes the replacement of the

loading boxes, sheave deck and all rock winder

guides, took place during a planned shut period

starting in March 2016.

The lifting of the 57-ton sheave deck took

place on 22 September 2016 using a 550‑ton

crane. All sheaves and related equipment have

been installed and aligned and roping up was

underway as this article was being written.

Commissioning, testing and licensing of both

winders and shaft systems will commence dur-

ing October and November 2016.

Considerable development work, of course,

forms part of the overall project. BRMO is

undertaking all the development and associ-

ated support work required at Nchwaning I

and III shafts ‘in house’ and is being assisted

by WorleyParsons, which is responsible for the

design, procurement and management of the

construction work. At Nchwaning II shaft, the

development has been contracted out to Aveng

Mining, which was due to complete its contract

during October 2016.

The development contract has included:

all satellite tips consisting of silos, tips, load-

ing facilities, top and bottom conveyors and

ramps between Seam 1 and Seam 2 reef planes

at Nchwaning II shaft; all transfer points; con-

veyor drives to Nchwaning I and II shafts; the

TMM workshop; and all crusher chambers.

Summing up WorleyParsons RSA’s involve-

ment in the BRP, Greyling says it demonstrates

the company’s abilities in virtually every

facet of underground mine construction and

development. “The Johannesburg office of

WorleyParsons RSA houses much of the mining

and shaft sinking expertise of the international

WorleyParsons group and in fact is the group’s

Global Centre for Excellence for precious

metals processing and underground mine

development,” he says. “All our skills have

been deployed at Black Rock and have contrib-

uted to what has been an extremely successful

project thus far.”

Photos: Charles Corbett on behalf of Assmang

Top:

The 11 m high graben

tie-in structure.

Above:

Conveyor in

progress from graben

tie-in to shaft system.