Background Image
Previous Page  43 / 60 Next Page
Information
Show Menu
Previous Page 43 / 60 Next Page
Page Background

April 2015

MODERN MINING

41

feature

COUNTRY FOCUS –

ZAMBIA

Above:

The sinking

headgear which is due to be

dismantled shortly (photo:

Arthur Tassell).

Top left:

Loading box

installation during

equipping phase.

Top right:

Mini-excavator

working on the 1 231 m

loading station level.

roughly 10 % being expatriates. Obviously we

want to reduce the proportion of expatriates

and we are therefore are putting a great deal of

effort into training. We have set up an e-learn-

ing centre and we also send trainees to our

Bentley Park training facility in South Africa.”

Nefdt says that with Murray & Roberts

Cementation’s Lubambe contract about to

finally finish (the company will be off-site

shortly) and the Synclinorium having only

months to run, the challenge now is to build

up the order book. “This is not an easy task in

the present market but we are currently tender-

ing on projects in the DRC and Ghana,” he says.

Commenting on the Synclinorium contract,

he says that this could rank as the last shaft to be

undertaken by Murray & Roberts Cementation

using conventional, South African-style shaft-

sinking methods. “The Group is moving

towards adoption of the model pioneered by

our Canadian company in which all activities

in the shaft-sinking cycle are undertaken in-

line, with no jobs taking place simultaneously,

which we believe will make for greater safety

and more efficiency,” he explains. “Having

said this, the traditional methods have served

us well on the Synclinorium, which has gen-

erally progressed well after some initial delays

relating to some problems with the civils and

also poor ground conditions for the first 200 m,

which proved tricky to negotiate and which

required extra support.”

The shaft sinking was completed at the end

of September last year, with one of the suc-

cesses along the way being a record 96 m of

sinking and lining during the month of August

2013 and one of the challenges the very wet

conditions, which required up to 24 000 litres

of groundwater a day to be pumped out of the

shaft. Nefdt’s colleague, Wyllie Pearson, who is

Senior Project Manager, also mentions that the

company intersected a 28 m dyke at one point.

“We sank through it without incident, a notable

achievement given that the rock was very hard

and susceptible to scaling. This necessitated

support to within 1 m of the shaft bottom in

order to increase worker safety.”

Innovations in the field of safety on the

Synclinorium contract by Murray & Roberts

Cementation have included the introduction of

a new system to replace the old system of hand