Annual Work Programme 2015
OTHER
ACTIVITIES
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D
TYNDP
Summer Supply Outlook
Winter Supply Outlook
GRIP
New TEN-E Regulation
Drafting (ENTSOG / TSOs)
Support to Regional Groups
Publication (ENTSOG / TSOs)
ACER Opinion
NETWORK
CODES
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D
Capacity
Balancing
Tariff
Amendment to CAM
Interoperability
incl. Data Exchange Rules
Network Code drafting (ENTSOG)
ACER (Opinion on Network Code)
Network Code implementation
Network Code implementation
finalized
Pre-/Comitology Process
ENTSOG ESTIMATED ACTIVITIES 2014–2015