Annual Work Programme 2015 |
15
CAPACITY ACTIVITY
2014
2015
S O N D J F M A M J J A S O N D
CAM
CAM NC auction calendar
CAM implementation – Booking Platform report
CAM Roadmap progress updates
CAM CNOTs specification (BRS +MIG)
INCREMENTAL CAPACITY
Deliver incremental proposal
Support and respond to ACER reasoned opinion
CAM change proposal development
CMP MONITORING/REPORTING
Report for 2014 Annual Report
Report for 2015 Annual Report
Development of changes / amendment or
support to other network codes
1)
Blue cells on the charts denote activity periods with green cells denoting key deliverables visible to external stakeholders
Image courtesy of FGSZ
PLAN
The following diagram shows the expected timeline and key activities for the work
within the ENTSOG Capacity stream in 2015:
1)
1) We have assumed a scoping phase for changes / amendments to be initiated during second half of 2014. Might include
changes / amendments initiated by capacity trading rules or identified cross-border capacity contract issues. Might also
be relevant for the BAL NC.