Previous Page  260 / 270 Next Page
Information
Show Menu
Previous Page 260 / 270 Next Page
Page Background

GAZETTE

JULY-AUGUST 1980

estimate for completion of the work

was just under four weeks. The

Defendants continued to work from

that time, though not continuously,

until the 13 November 1974, when the

Plaintiffs purported to repudiate the

contract

and engaged

another

contractor who laid an alternative

type of roof, namely an asphalt roof.

The

initial

period

of

the

Defendants' work, commencing on

September 24, 1974 had ceased on 2

October 1974, when the Defendants

left the site, as the Defendants were

awaiting the completion of work by

other contractors to permit them to

continue the further insulation of the

roof. The Defendants complained

that during that initial period of work

and during the period of their absence

from the site extensive damage had

been caused to the roof and that

when they returned to the site on

October 18, 1974 they were faced

with an extremely difficult problem.

The Defendants further complained

that between that time and the 13

November 1974 (when the purported

repudiation by the Plaintiffs took

place) damage continued almost

uninterrupted despite protests and

complaints on their part.

On 9 November 1974 a major leak

through the roof in various places

occurred during, admittedly, very wet

weather. As a result the Plaintiffs'

Architect was called to the shopping

centre and a series of meetings were

held with the Defendants when

proposals were made by the

Defendants for repair. The Plaintiffs'

Architect expressed the point of view

that the Defendants had completely

failed to carry out the system as an

effective and efficient system and that

their explanations for the failure were

unacceptable; he accordingly advised

the Plaintiffs to engage another

contractor. The advice was accepted

and the Plaintiffs purported to

repudiate their contract with the

Defendants on 13 November 1974.

Changes in the design of the basic

roof structure had been made by the

Plaintiffs resulting in a change in the

fall of the roof, and the case was

made by the Defendants that this was

a major contributing factor to the

failure of their roof insulating

operation.

It was undisputed at the hearing

that a water-tight or weather-tight

roof was not achieved as at 13

November 1974, and the dispute

between the P'aintiffs and the

Defendants on liability turned on two

contentions of the Defendants',

namely.

(i) The Defendants contention that

they were at the commencement

of the work supplied with an

architect's

drawing

which

indicated that the fall on the roof

would be one in one hundred and

that without their knowledge or

approval this was altered to a fall

of one in three hundred only with

the consequence that there was a

marked lack of drainage on the

roof causing the lodging of water

which destroyed the process

which they were applying.

(ii) The

Defendants'

further

contention that during the entire

process of the work being carried

out by them the roof was

subjected to damage due to the

negligence

of

the

Plaintiff

Contractors, their servants or

agents and of the servants or

agents of other sub-contractors.

Held

(per Finlay, P.):

(a) That on the evidence the

alteration and design of the roof

by the Plaintiffs was not the

cause of the failure nor was the

change in the fall of the roof

unknown to the Defendants

before

their

operations

commenced.

(b) That

the

Defendants

held

themselves out as specialists in a

specialist

form

of

roofing

insulation and that under the

term undoubtedly implied into

the contract, the Defendants

would use reasonable skill and

care in the carrying out of their

work and that the Defendants

had a duty to provide for and

insist upon any special precautions

that they required. In the

circumstances the repudiation of

the contract by the Plaintiffs on

13 November 1974 was justified

as the Defendants had failed in

the fundamental term of the

contract namely to provide an

effective waterproofing of the

roof within a reasonable time.

Accordingly, the Plaintiffs claim

for damages was successful.

Dundalk Shopping Centre Limited

v. Roofspray Limited,

High Court,

(Finlay P. 21 March 1979 —

unreported.

EXTRADITION

Robbery with violence contrary to

Section 8 of the English Theft Act,

1968,

does correspond to robbery

with violence under the Larceny Act

1916,

in this State, provided the

recital of the offence in the warrant

identifies the offence by reference to

the factual components relied on and

not merely because the offences have

the same name. Sections 47(2) and

5<X2Xc)

of Extradition Act,

1965,

considered.

Extradition was sought on a warrant

which recited that the Plaintiff on a

specified date at a specified place in

Middlesex "did rob M.B. of £281 in

cash and immediately before doing

so, used force, to wit personal

violence, to the said M.B." In a

separate entry in a separate para-

graph in the warrant the offence was

said to be contrary to Section 8 of the

Theft Act, 1968.

The sole matter in issue was

whether (as required for the issue of a

direction under Section 50(2) (c) of

the Extradition Act, 1965) the offence

so specified "does not correspond

with any offence under the law of the

State which is an indictable offence

or is punishable

op

summary

conviction by imprisonment for a

maximum period of at least six

months." The fact that this test is

expressed in a negative form (both in

Sections 47(2) and 50(2) (c) of the

Act of 1965) was not indicative of

where the onus of proof lay; it merely

laid down that, for the allowance of

this exemption from extradition, the

Court had to be of the opinion that in

the circumstances of the case there

did not exist dual criminality to the

extent required for the specified

correspondence of offences. The

requirement for extradition was

satisfied when correspondence was

shown between the specified offence

and

any

offence which either was an

indictable offence or carried a punish-

ment on conviction of a maximum

term of six months imprisonment.

The District Justice had held that

the

offence

in

the

warrant

corresponded with robbery with

violence, contrary to the Larceny Act,

1916. When the Plaintiff instituted

these proceedings in the High Court

seeking a direction that he be released

under Section 50(2) (c) of the Act of

1965 the High Court (per McMahon

J.) held that the specification in the