Background Image
Previous Page  16 / 32 Next Page
Information
Show Menu
Previous Page 16 / 32 Next Page
Page Background

January 2015

Housing

and demographic representation.

Development cost contributions

include the national and provincial

government and eThekwini R10,4

billion, Tongaat-Hulett R14,3 billion,

the South African Sugar Association

(SASA) R1,1 billion, bringing the total

to R25,8 billion. For the development

costs in Phase 1 - 659 ha of land was

acquiredwith over half a billion rands

ring fenced – R669,4 million was ap-

proved by Province and R511,6mwas

paid from the province to eThekwini

Municipality. So far, the private sec-

tor has invested R350

million.

T

here are challenges

says Pillay. A Memoran-

dum of Understanding

between the Depart-

ment of Transport and

the City, which determines the cost

sharing percentages is still under

discussion. Also, the agreement for

funding and cost sharing to build the

bridge over the N2, which is a key link-

age and forms part of the Integrated

Rapid Public Transport Network, has

still to be finalised. The eThekwini

Transport Authority has indicated

that there is an opportunity to in-

clude this into the M41/N2 contract

with SANRAL. The design has been

finalised andwill provide a significant

link to Cornubia via Gateway opening

up this portion of the site for housing

development.

Poor geotechnical ground condi-

tions, which could not be determined

prior to the implementation stage,

increased the costs. The wetland

drainage line occupies 28% of the

site and added an additional R46

million with the accommodation of

imported fillmaterial and spoiledma-

terials. It also meant a three month

delay in construction. To comply with

municipal bylaws and stormwater

management, a further R17,5 million

was required to provide 2 187 units

with gutters and downpipes. Fund-

ing for bulks, such as roads and cost

sharing agreements that were not

concluded increased the extra costs.

Lengthy Supply Chain Management

processes, appeals and litigation

delayed the roll out by up to eight

months. Demand for housing exceeds

the planned supply. Ensuring inte-

grated delivery also meant including

temporary schools for scholars.

Another challenge was the Noise

Contour Restriction on use of land

for residential development as a

large portion of the land falls within

eThekwini and was zoned for general

business and light industrial use.

To qualify for the Densification

Subsidy developers will need to

maximise their investment on the Bus

Rapid Transport routes, which will

make the transport nodemore viable

with the higher densities.

Pillay says that one of the lessons

learned was to identify potential

beneficiaries at an early stage, since

delays in providing documentation

often meant that houses could not

be handed over and were left unoc-

cupied for an extended

period of time. He says,

“Allow for adequate finan-

cial authority to manage

the variations, as obtain-

ing additional authority

is a lengthy process.” It is

important to consider the separa-

tion of top structure and civil works,

the framework on employment op-

portunities and multi procurement

strategies.

The private sector will develop

10 000 units, bulk will be provided

for affordable housing catering for

households earning less than R18 000

per month. There is an opportunity

says Pillay to pilot an Employee As-

sisted Housing (EAH) scheme within

the next few years using various

subsidy programmes such as FLISP.

There will be various social

‘The initial phase will create a walkable

residential precinct structured around

courtyards and well defined streets as the

basis for building a sense of community.’