Interconnection Croatia-Bosnia and Herzegovina (South)
General Information
Promoter
Plinacro Ltd
Operator
Plinacro Ltd
Host Country
Croatia
Status
Planned
Website
Project's URL
Publication Approval Status
Approved
Sponsors
Croatian part of both options
Plinacro d.o.o.
100%
parts in B&H
BH Gas
100%
TRA-N-302
Project
Pipeline including CS
Non-FID
Update Date
13/07/2016
Advanced
Description
South Interconnection of Croatia and B&H - the pipeline is a new supply route for Bosnia and Herzegovina that will enable the reliable and
dievrsifed natural gas supply. The pipeline will enable the flow of IAP to Bosnia and Herzegovina
Regulatory Decisions and
similar material conditions
Enabled Projects
Project Code Project Name
TRA-N-068 Ionian Adriatic Pipeline
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Posušje
Plinacro Ltd
2021
BA
HR/IAP
81.0 GWh/d
Plinacro Ltd
2021
HR/IAP
BA
81.0 GWh/d
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 289 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |
66