Expected Gas Sourcing
LNG (HR), It will be gas from Croatia transport system, Croatian UGS and Croatian planned LNG terminaland Baumgarten via Slovenia
Time Schedule
Grant Obtention Date
Delay Since Last TYNDP
The start of the construction has been postponed until 2020.
Delay Explanation
It depends on the agreement with Republika Srpska (B&H)
PCI Details
PCI Benefits
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation
prior to the commissioning of the project, Project concerns investment in reverse flow capacity
General Criteria Fulfilled
No
Specific Criteria Fulfilled
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
The project is fullffilling and the folloving criteria: Lifting isolation for Bosnia and Herzegovina, reducing bottelnecks, will improve remaining
flexibility, will enable source and route diversification
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Slobodnica - Bosanski Brod
4 million m3 daily
700
6
Total
6
Schedule
Start Date
End Date
Pre-Feasibility
Feasibility
FEED
Market Test
08/2016
Permitting
01/2011
01/2019
Supply Contracts
FID
12/2017
Construction
01/2018
01/2019
Commissioning
2019
2019
NDP and PCI Information
Part of NDP
Yes (2017-2026)
NDP Number
1.13
Currently PCI
No
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
No
Exemption in entry direction
70.00%
Exemption in exit direction
30.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 266 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |