Time Schedule
Grant Obtention Date
Delay Since Last TYNDP
PCI Details
PCI Benefits
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation
prior to the commissioning of the project, Project concerns investment in reverse flow capacity, Project aims at supplying directly or indirectly
at least two Member States
General Criteria Fulfilled
Yes
Specific Criteria Fulfilled
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Project will connect several, in the future exceptionally important, points of the Croatian gas transmission system. It is the future strategic gas
transmission connector of great significance and is an integral part of the North – South European Corridor named as the North-South (Baltic –
Adriatic) Gas Connection. Its purpose is linking the Polish and the Croatian LNG (Liquefied Natural Gas) solutions. This gas pipeline (as well as
all the pipelines to which it connects and the associated gas nodes) will provide gas transmission in all directions, i.e. it will satisfy all
transmission requirements and will maximise the value of the IAP and LNG projects in Croatia and the region. In addition, it will increase the
use of the existing system and the new interconnection with Hungary.
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Omišalj-Zlobin
1,000
18
Total
18
Schedule
Start Date
End Date
Pre-Feasibility
Feasibility
FEED
Market Test
08/2016
Permitting
07/2009
01/2018
Supply Contracts
FID
01/2017
Construction
01/2017
05/2018
Commissioning
2018
2018
NDP and PCI Information
Part of NDP
Yes (2017-2026)
NDP Number
1.17
Currently PCI
No
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
No
Exemption in entry direction
70.00%
Exemption in exit direction
30.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 287 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |