Interconnection Croatia/Slovenia (Lučko - Zabok - Rogatec)
General Information
Promoter
Plinacro Ltd
Operator
Plinacro Ltd
Host Country
Croatia
Status
Planned
Website
Project's URL
Publication Approval Status
Approved
Sponsors
Plinacro
100%
TRA-F-86
Project
Pipeline including CS
FID
Update Date
13/07/2016
Advanced
Description
New pipeline which will upgrade the existing interconnection Croatia/Slovenia. Along with the existing interconnection Karlovac-Lučko-Zabok-
Rogatec, a new gas pipeline system has been planned which would significantly increase the capacity of the interconnection of the Croatian and the
Slovenian gas transmission systems in this direction. Considering almost all existing and new supply directions in the surrounding region and the
Croatian storage potentials this opens significant transit potentials in both directions. Along this transit route, it is planned to upgrade the capacity
to 5 bcm/y.
Regulatory Decisions and
similar material conditions
Enabled Projects
Project Code Project Name
TRA-N-1057 Compressor stations 2 and 3 at the Croatian gas tranmission system
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Rogatec
Plinacro Ltd
2019
HR
SI
162.0 GWh/d
Plinacro Ltd
2019
SI
HR
162.0 GWh/d