Expected Gas Sourcing

Algeria, Caspian Region, LNG (QA,US)

Benefits

Main Driver

Market Demand

Main Driver Explanation

Schedule towards commissioning will be affected by binding requests from shippers

Benefit Description

IGB development is not associated with a specific supply source. The pipeline can interact with alternative supply sources - such as, Southern Corridor

pipeline gas, LNG through Greece/ Turkey.

Delay Explanation

Extension in permitting procedures for authorization of construction and of regulatory TPA procedure for new gas infrastructure

Barriers

Barrier Type

Description

Regulatory

The regulatory framework has to provide more streamlined process for decisions on TPA regime and licencing, and ensure a viable rate of financial return

from the investment.

Permit Granting

Affected by delays

Political

Government support expected on issues such as streamlined permitting and regulatory decisions on commercial development, availability of financial

incentives

Market

Development of the networks of neighboring gas TSOs to be interconnected with IGB should be incentivised to ensure proper technical conditions for

expected additional flows. Better integration of the gas transmission networks in the overall region affected by IGB must also be achieved in order to

supply gas from IGB to the wider SEE region.