Benefits

Main Driver

Regulation SoS

Main Driver Explanation

Project will enable the reverse flow in all interconnection points.

Benefit Description

Construction of such facilities is neccessary due to the opening of the gas market, as well as providing sufficient transmission capacities and natural gas

delivery pressure conditions and for development of the gas market in Croatia and the neighbouring countries. Compressor stations will significantly

increase efficiency of the Croatian gas transmission system.

PCI Details

PCI Benefits

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation

prior to the commissioning of the project, Project concerns investment in reverse flow capacity

General Criteria Fulfilled

Yes

Specific Criteria Fulfilled

Competition, Market Integration, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

11/2014

03/2015

FEED

Market Test

08/2016

Permitting

06/2015

12/2017

Supply Contracts

01/2017

FID

04/2015

Construction

01/2017

12/2017

Commissioning

2017

2017

NDP and PCI Information

Part of NDP

Yes (2017-2026)

NDP Number

5.1,

Currently PCI

Yes (6.26.3)

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Not Applicable

Considered Tariff Regime

Not Applicable

Applied for Exemption

No

Exemption Granted

No

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%