Expected Gas Sourcing
Caspian Region, Russia, Other Central Asian, Middle Eastern and East-Mediterranean sources.
Time Schedule
Grant Obtention Date
Delay Since Last TYNDP
1 year
Delay Explanation
Lack of interest from the market
PCI Details
PCI Benefits
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation
prior to the commissioning of the project, Project concerns investment in reverse flow capacity
General Criteria Fulfilled
Yes
Specific Criteria Fulfilled
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Komotini-Thesprotia
total length of new pipes
1,067
613
58
Total
613
58
Schedule
Start Date
End Date
Pre-Feasibility
Feasibility
FEED
Market Test
Permitting
Supply Contracts
FID
Construction
Commissioning
2023
2023
NDP and PCI Information
Part of NDP
Yes (Development Plan NNGS 2015-2024)
NDP Number
2.2.1.4
Currently PCI
Yes (7.1.7)
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
Not Relevant
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%