Benefits
Main Driver
Market Demand
Main Driver Explanation
Benefit Description
Diversification of sources of energy, routes and supplies; increasing the degree of interconnectivity between the gas transmission systems of the two
countries; safety, reliability and interoperability of interconnected energy networks, including enabling bidirectional gas flows; contribution to the
establishment of the South-Eastern European regional gas market.
Time Schedule
Grant Obtention Date
06/09/2010
Delay Since Last TYNDP
12 months
Delay Explanation
Problems during the construction phase. The complicated geological structure, under the bottom section of the Danube river bad to be
crossed by Horizontal Directional Drilling, produced significant delays as a result of unpredictable factors.
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Giurgiu-Ruse
500
25
Total
25
Schedule
Start Date
End Date
Pre-Feasibility
Feasibility
FEED
Market Test
Permitting
Supply Contracts
FID
Construction
01/2016
Commissioning
2016
2016
NDP and PCI Information
Part of NDP
No (The project is in the final stage of the
construction works and will be
comissioned during 2016.)
NDP Number
Currently PCI
No
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
Not Relevant
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 468 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |
228