Table of Contents Table of Contents
Previous Page  454-455 / 610 Next Page
Information
Show Menu
Previous Page 454-455 / 610 Next Page
Page Background

Benefits

Main Driver

Market Demand

Main Driver Explanation

Benefit Description

Diversification of sources of energy, routes and supplies; increasing the degree of interconnectivity between the gas transmission systems of the two

countries; safety, reliability and interoperability of interconnected energy networks, including enabling bidirectional gas flows; contribution to the

establishment of the South-Eastern European regional gas market.

Time Schedule

Grant Obtention Date

06/09/2010

Delay Since Last TYNDP

12 months

Delay Explanation

Problems during the construction phase. The complicated geological structure, under the bottom section of the Danube river bad to be

crossed by Horizontal Directional Drilling, produced significant delays as a result of unpredictable factors.

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Giurgiu-Ruse

500

25

Total

25

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

Market Test

Permitting

Supply Contracts

FID

Construction

01/2016

Commissioning

2016

2016

NDP and PCI Information

Part of NDP

No (The project is in the final stage of the

construction works and will be

comissioned during 2016.)

NDP Number

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 468 of 620

Current TYNDP : TYNDP 2017 - Annex A

Southern Corridor GRIP 2017–2026 Annex B |

228