NTS developments in North-East Romania
General Information
Promoter
SNTGN Transgaz SA
Operator
SNTGN Transgaz S.A.
Host Country
Romania
Status
Planned
Website
Project's URL
Publication Approval Status
Approved
Sponsors
SNTGN Transgaz S.A.
100%
TRA-N-357
Project
Pipeline including CS
Non-FID
Update Date
01/09/2016
Advanced
Description
Development of the Romanian gas transmission system in order to improve the gas supply in the North –East region of Romania and to increase
transmission capacities so as to improve gas supply in the area as well as to ensure transmission capacities in the perspective offered by the new
pipeline for the interconnection of Romania and the Republic of Moldova. The scope of the project is the achievement of the following objectives: �
The construction of a new gas transmission pipeline Dn 700, Pn 55 bar, in the direction Onești-Gherăiești, 104 km long; � The construction of a new
gas transmission pipeline Dn 700, Pn 55 bar, in the direction Gherăiești-Lețcani, 61 km long; � The construction of a gas compressor station at
Onești, with an installed power of 6 MW, with 2 compressors of 3 MW each; � The construction of a gas compressor station at Gherăiești with an
installed power of 4 MW, with 2 compressors of 2 MW each.
Regulatory Decisions and
similar material conditions
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 478 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |
229