M8 Kalce - Jelšane
General Information
Promoter
Plinovodi d.o.o.
Operator
Plinovodi d.o.o.
Host Country
Slovenia
Status
Planned
Website
Project's URL
Publication Approval Status
Approved
Sponsors
Plinovodi
100%
TRA-N-101
Project
Pipeline including CS
Non-FID
Update Date
22/05/2016
Non-Advanced
Description
Interconnector with the transmission system of the Croatian TSO, LNG North Adriatic, as well as connection of new municipalities. Cross-border
transmission.
Regulatory Decisions and
similar material conditions
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Rupa (HR) / Jelšane (SI)
Plinovodi d.o.o.
2022
HR
SI
414.0 GWh/d
Plinovodi d.o.o.
2022
SI
HR
414.0 GWh/d
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 513 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |
300