introduction FY2014

International Drive Extension Phase 3

Project Description: Design and Construct International Extension (0.84 miles) from the northern (future) terminus at the intersection with McCrimmon

Parkway/Evans Road Extension northward to the intersection with Airport Boulevard at the current intersection with Slater Road (color coded green on the project

map below). On the 2009 Transportation Plan the road is shown as a 4-Lane Collector (57 feet b-b) within a 97 foot ROW.

Town Goals

Manage Resources

Invest in Infrastructure and Transportation

Serve the Community

Provide a Safe Community

Benefits of Project:

Lead Department:

Public Works Department

1. Reduces congestion and truck traffic on Airport Blvd.

Date Added to CIP:

2009

2. Provides connectivity between both Aviation Parkway and the

Review Date:

30-Oct-12

McCrimmon Extension and Airport Blvd.

Design Start Year:

2020

3. Will reduce congestion and truck traffic on Aviation Pkwy. & NC 54 Construction Start Year:

2021

Estimated Project Costs:

$9,930,844

Additional Staffing Required:

No

Number of New Positions:

0

Operations and Maintenance Estimates

2022

2023

2024

2025

2026

O&M Remarks:

Equipment and Furniture

Utilities

$

1,200 $

1,200 $

1,200 $

1,200 $

1,200

Maintenance

$

1,000 $

1,000 $

1,000 $

1,000 $

1,000

Supplies

Personnel

Other Funding

Sources and

Related Revenue

Projections

None

Financing Plan

Bond 7.5/5/2.5

Tax on $100k

Debt Service Schedule

Tax Base

¢ Tax

$

234.50

1 2022

$ 1,142,047 $ 4,299,514,804

2.66

$

26.60

2 2023

$ 1,112,255 $ 4,428,500,249

2.51

$

25.10

3 2024

$ 1,082,462 $ 4,561,355,256

2.37

$

23.70

4 2025

$ 1,052,670 $ 5,245,558,544

2.01

$

20.10

5 2026

$

774,606 $ 5,402,925,301

1.43

$

14.30

6 2027

$

754,744 $ 5,565,013,060

1.36

$

13.60

7 2028

$

734,882 $ 5,731,963,452

1.28

$

12.80

8 2029

$

715,021 $ 5,903,922,355

1.21

$

12.10

9 2030

$

695,159 $ 6,081,040,026

1.14

$

11.40

10

2031

$

675,297 $ 6,263,471,227

1.08

$

10.80

11

2032

$

655,436 $ 6,451,375,363

1.02

$

10.20

12

2033

$

635,574 $ 7,096,512,900

0.90

$

9.00

13

2034

$

615,712 $ 7,238,443,158

0.85

$

8.50

14

2035

$

595,851 $ 7,383,212,021

0.81

$

8.10

15

2036

$

575,989 $ 7,530,876,261

0.76

$

7.60

16

2037

$

556,127 $ 7,681,493,786

0.72

$

7.20

17

2038

$

287,995 $ 7,835,123,662

0.37

$

3.70

18

2039

$

278,064 $ 7,991,826,135

0.35

$

3.50

19

2040

$

268,133 $ 8,151,662,658

0.33

$

3.30

20

2041

$

258,202 $ 8,966,828,924

0.29

$

2.90

Comments:

Construction Cost includes the road, purchase of ROW, street lights, 12 inch watermain and 10%

contingency.