Previous Page  16 / 60 Next Page
Information
Show Menu
Previous Page 16 / 60 Next Page
Page Background

14

MODERN MINING

June 2017

MINING News

AIM-listed Rainbow has provided a further

update on its Gakara rare earth project

in Burundi. Gakara is one of the highest

grade rare earth element mining projects

globally with an estimated in-situ grade of

47-67 % Total Rare Earth Oxide (TREO).

Mining work at Gakara commenced in

April 2017, focusing on the initial mining

site at Gasagwe. This will be Rainbow’s pri-

mary source of ROM ore during 2017/18.

The labour force has concentrated on

stripping overburden at the surface of

Gasagwe, thereby exposing the targeted

‘main vein’ to a height of at least 1 m along

its current exposed strike length. The

uncovered vein will be relatively simple to

extract and stockpile as required.

There have also been discoveries of sev-

eral previously unrecorded veins which will

also be extracted and added to the ROM

stockpile prior to the commissioning of the

processing plant at Kabezi.

Rainbow reports that work continues

on the improvements to the approximately

2,3 km long Gasagwe access road from the

Mining starts at Gakara’s first production site

Mining work at Gakara began in April 2017, focusing on the initial mining site at Gasagwe (photo: Rainbow Rare Earths).

nearest town of Mutambu using local con-

tractors. The road upgrade is required for

the haul trucks to transport ROM ore to the

processing plant, hence there is no impact

on current mining operations during its

construction.

By the end of May 2017, the number

of local workers trained and inducted by

Rainbow’s team had doubled to 80 from

the initial 40. As well as being trained to

assist with mining activities, the newwork-

ers will also be assigned to exploration and

road maintenance roles.

Rainbow’s planned exploration activities

over the coming months will incorporate

both greenfield and brownfield areas. The

focus of the greenfield work will be on

areas within the company’s existing explo-

ration licence, which have previously not

been explored. The company will use tech-

niques that have proved successful during

previous work in other areas.

Brownfield work will focus on areas

within Rainbow’s mining licence where

significant rare earth discoveries have

already been made, with the purpose of

delineating further tonnage for future

mining. Tasks to be undertaken include

trenching, mapping, gravity surveying,

and a trenching/terracing prospecting

programme with a view to uncovering,

accurately mapping, and sampling the

in-situ sources of large bastnaesite blocks

previously discovered on the surface in the

Kiyenzi area.

Rainbow’s ROMore processing plant will

be situated at Kabezi, 10 km due south of

Bujumbura and approximately 20  km from

the company’s mining areas. The site com-

prises relatively flat ground, close to the

shore of Lake Tanganyika, and is located on

a main asphalt road. This will provide ease

of access for the container trucks collecting

rare earth concentrate for export.

Rainbow’s selected EPCM contrac-

tor, Obsideo Consulting of South Africa,

continues to make good progress with

equipment procurement and expects the

first shipment of containers to leave South

Africa during June.

Big increase in output at Frontier operation

Frontier mine, owned by Eurasian Resources

Group (ERG), delivered more than 107 kt of

contained copper in concentrate in 2016,

an increase of 35 % on 2015 output.

Frontier – originally built by First

Quantum – is ERG’s flagship mine in the

DRC and is the cornerstone of the Group’s

copper business in Africa. In 2016 the plant

improved its performance across many key

indicators.

A revised production plan was launched

by ERG in late 2015 to increase long-term

copper production at Frontier by improving

the efficiency and effectiveness of its oper-

ating model.

The growth was the outcome of con-

siderable operational improvements and

investment while the mine also changed

the way it deployed contractors. Major ben-

efits were realised from Q2 2016 onwards,

resulting in a steady supply of copper ore,

improved plant feed grades and plant

throughput tonnages.

John Robertson, Frontier Mine President

– General Manager, said: “The production

figures at our flagship Frontier mine are

very encouraging and I am proud of what

the team has achieved. This is a major step

forward for the Group and supports ERG

Africa’s strategy to become a regional cop-

per and cobalt champion. Our people are

ERG’s greatest asset and their ability to plan,

embrace change and deliver solid results is

commendable.

“The achievements at Frontier mine play

a key part in forming a balanced produc-

tion system alongside ERG’s copper and

cobalt asset portfolio in Africa, which also

includes Boss Mining, Comide, Chambishi

Metals, and the Metalkol Roan Tailings

Reclamation project.”