17
CONSTRUCTION WORLD
OCTOBER
2016
This provided WBHO sufficient time to power float the slabs from the
time the readymix concrete was delivered to the site,” Ross says.
WBHO started working on the premium commercial development
at No 5 Silo in February 2015 and completed the building in July this
year, providing five floors of 15 000 m
2
of additional office space at
the V&A Waterfront.
The building’s high quality concrete finishes are complemented
by its impressive façade comprising glass, aluminium, tiles and Rhine
zinc, while 15 steel bridges connect the two separate seven storey office
blocks above an internal cobblestone road.
Work on the No 4 Silo project is also nearing its September
completion date. Set to be completed in March 2017, the No 3 Silo
development comprises three residential tower blocks. The highest at
12 storeys provides the best setting of all residential apartments at the
precinct. All these structures were built off the 30 000 m
2
two storey car
park, which WBHO completed in April this year.
Brooks says that it was built in phases to accommodate the
various access dates for the construction of the three buildings. Sheet
piling had to be installed all the way around the precinct to retain the
surrounding area, before the contractor could start excavating the
basement down to 1,8 metres below sea level.
The entire project was divided into the three silo developments
with their own construction programmes however, there was still a
strong element of interface between them.
Already home to multiple award winning No 1 and No 2
Silo developments, the historic Grain Silo complex on
the V&A Waterfront is being redeveloped to house the
Zeitz Museum of Contemporary Art Africa (Zeitz MOCAA).
There are also four new mixed-use, sustainable
developments under construction in the district
including new corporate offices, a residential devel-
opment, a Virgin Active Classic Health Club and a
mid-range internationally branded hotel, as well as over
1 050 additional parking bays. When completed in early
2017, approximately 2 500 people will work at the Silo
district daily.
“For example, the handover of No 5 Silo, which is located right in the
centre of the congested construction site, had to be carefully managed
to allow safe entry and exit for people, as well as deliveries,” he says.
The project employed well over 1 000 people when it peaked, and
achieved 2 million LTIF. This is an incredible achievement, and clearly
one of the other reasons why WBHO has remained the contractor of
choice on this project.
AfriSam, as the leading concrete material supplier in the
Western Cape, is well positioned to supply high demand and
speciality mix designs such as the Silo Precinct project.
ABOVE:
AfriSam took a proactive stance in this
supply contract with upfront intensive testing
to achieve the correct concrete mix, through to
extensive planning to ensure the timeous delivery.
RIGHT:
AfriSam’s scope of supply to Silo No 3, 4 and 5
includes standard and speciality concrete mixes. This
includes the complex column mix which was designed
specifically for the No 5 Silo project.