ACTIVITY

GOAL

DELIVERABLE & 

COMPLETION DATE

CONSULTATION WITH

STATUS / COMMENTS

MARKET AREA

Balancing

Management of BRS for Balancing

(potential change procedures or

new BRS)

Publish the updated BRS for

Nomination and Matching with the

Common Data Exchange Solutions

Publication on 7 November 2016

Stakeholders, TSOs

Completed

Implementation support and

sharing of implementation

experiences

Organize a joint ACER/ENTSOG

Workshop on Balancing

Organised Workshop on

7 November 2016

Stakeholders, TSOs,

NRAs and ACER

Completed

Implementation monitoring

Publish the first ENTSOG report on

the implementation for Balancing

to assess implementation status as

of 1 October 2015.

Publication on 8 June 2016

TSOs and ACER

Completed

Potential functionality process

for BAL

Provide stakeholders the

possibility to raise and discuss

the implementation, functional and

operational issues as well as involve

stakeholders into prioritisation

and propositions of solutions

No issues were raised

in 2016

Update on implementation

status report

Publish the second ENTSOG report

on the implementation for Balancing

to assess implementation status as

of 1 October 2016.

Launched questionnaire to TSOs

in December 2016

TSOs and ACER

On-going

Tariffs

Support during the TAR NC

comitology period

Ensure the adoption of the TAR NC

On-going in 2016, expected

completion early 2017

EC, ACER, TSOs

On-going

Implementation discussion

Facilitate the efficient implementation

of the TAR NC

Start Implementation Document

and prepare for Implementation

Workshop, both to be finished early

2017

TSOs, NRAs, ACER,

Stakeholders

On-going

Develop TAR implementation

monitoring

Prepare for the drafting of

Implementation Monitoring report

Start process in 2016 so that

ENTSOG is on time to launch ques-

tionnaire and collect data before

31 Dec 2017 and prepare the report

by 31 March 2018

TSOs and ACER

On-going

Develop TAR effect monitoring

Prepare for the drafting of

Effect Monitoring report

Start process in 2016 so that

ENTSOG is on time to launch ques-

tionnaire and prepare the report by

31 March 2018

TSOs and ACER

On-going

Setting up stakeholder process for

TAR FUNC

To prepare for functionality process

to facilitate and resolve early

identification of issues/challenges

Include the TAR NC in the J-FUNC

process in Q2/2017

TSOs, NRAs, ACER,

Stakeholders

On-going

18 |