Image courtesy of Ontras
ACTIVITY
GOAL
DELIVERABLE &
COMPLETION DATE
CONSULTATION WITH
STATUS / COMMENTS
SYSTEM OPERATION AREA:
PROJECT PLAN FOR TRANSPARENCY WORKING GROUP
Additional tools for
Transparency Platform
Increased usability and user
friendliness
Several new TP functionalities
were implemented during 2016
with aim of enhancing data
usability and publication com-
prehensiveness
Gas TSOs, TP users and
other stakeholders
Completed as planned
10th public workshop on
Transparency
Ensure transparent dialog with
stakeholders
8 December 2016
Gas TSOs, TP users,
ACER, EC
and other stakeholders
Completed
Improvement of TP data quality
Enhance data publication
comprehensiveness and usability
Ongoing process of data
publication monitoring
On-going activity,
in progress
Improvement of TP data
frequency uploads
Publish physical flows in hourly
granularity and frequency for cross-
border points from 1 May 2016
39 TSOs have started to
publish more frequently than
required by the regulation
during 2016
Gas TSOs, EFET
80% complete
The remaining TSOs will
follow
Follow-up to REMIT
Ensure timely implementation and
compliance of TSOs with REMIT re-
quirements
7 April 2016
ensuring compliance ongoing
activity
Completed
On-going activity,
in progress
Follow-up to NC transparency
obligation
Ensure timely implementation of new
transparency requirements.
Ongoing effort
Gas TSOs, ENTSOG
Working Groups,
TP users and other
stakeholders
Ongoing activity,
in progress
TP collaboration tool for
information provision
Utilise the TP framework in emergency
situations
Ongoing effort
RCSG KG
On-going activity
embedded in the RCSG
KG under Interoperability
20 |
ENTSOG Annual Report 2016