Boralex Inc and Témiscouata regional county municipality

have announced the commercial commissioning of the first

23.5MW from the Témiscouata wind farms.

“The Témiscouata I community wind power project is

promising from both an environmental and economic

perspective. To date, the two wind farms under construction

have generated more than $6 million in direct economic

spin-offs in Témiscouata as well as a host of indirect benefits,”

noted Témiscouata municipality warden Guylaine Sirois.

“The wind farms will bring in steady revenues for the next 20

years that will help support our municipalities and economic

development in our region,” she continued.

The Témiscouata II wind farm, with a capacity of 51.7MW,

is under construction, with the roads and the foundations

completed on target to the initial schedule. Commissioning is

expected in late 2015.