Previous Page  26 / 90 Next Page
Information
Show Menu
Previous Page 26 / 90 Next Page
Page Background

2 15

BEST

PR

O

JECTS

22

CONSTRUCTION WORLD

DECEMBER

2015

WBHO was awarded the Kusile Ash

Dam contract in 2011, but due to

permitting issues, construction only

commenced in the third quarter of 2012.

A major component of this contract is to

line the proposed ash dam area. This opera-

tion consists of a complex layer of different

liner materials all aimed at preventing

harmful substances from coming into

contact with the environment. The sequen-

tial set of operations involved in achieving

this target is summarised in the following

major operations:

Civil Engineering Contractors

A1

1. Topsoil removal: vegetation is cleared

and grubbed from the work area, topsoil

is then removed and stockpiled for later

reclamation works

2. Surface preparation: Exposed soil is

ripped to 200 mm depth, moisturised,

blended spread and compacted to achieve

a smooth organic matter and stone free

surface to receive the first bottom HDPE

liner layer.

3. Bottom liner: The approved soil surface

is then covered with a 2 mm double

textured liner, welded, quality checked

and handed over.

4. Bottom geotextile: The bottom HDPE liner

is then covered and protected with an A8

Bidim layer.

5. Geo-cell: A 50 mm geo-cell matt is stapled

together and stretched out over sloped

areas, this is to prevent erosion in the leak

detection area.

6. Washed river sand: a 100 mm washed

river sand laver is spread over the Geo-cell

and A8 bidim layer, which acts as a leak

detection layer.

7. GCL: A Geosynthetic Clay Liner layer is

then placed to cover the washed river

sand layer.

8. Top liner: the GCL is covered with

a 2 mm double textured liner,

welded, tested, quality checked and

handed over.

9. Top Geotextile: The top 2 mm HDPE liner is

protected by an A8 Bidim layer.

Project information

• Company entering: WBHO Construction

• Project start date: April 2012

• Project end date: April 2016

• Client: Eskom

• Project team: Kusile Executive Team

• Main contractor: WBHO Construction

• Principal agent: Eskom

• Project manager: WBHO Construction

• Consulting engineer: Worley Parsons

• Design engineer: Knight Piésold

Consulting Engineers

• Project value: R1,1-billion

Kusile Combustion Waste Terrace

10. Drainage layer: The liner and associated

sandwich is them covered with a 300 mm

drainage layer of G5 gravel.

11. Drainage pipes: A network of 50 mm

perforated drainage pipes is then installed

200 mm deep in the drainage layer, cradled

by washed sand and rapped in A4 Bidim.

12. Tie in: the perimeter of the HDPE liner ties

into a leak detection channel connected to

a concrete drain. This tie in consists of two

rubber gaskets between the concrete and

a stainless steel baton with holding down

bolts every 250 mm.

The first two contractual milestone dates on

this contract was achieved and final comple-

tion is expected within the allotted contract

period in 2016.