Previous Page  28 / 90 Next Page
Information
Show Menu
Previous Page 28 / 90 Next Page
Page Background

2 15

BEST

PR

O

JECTS

24

CONSTRUCTION WORLD

DECEMBER

2015

South African Breweries has invested

in a new state of the art maltings

plant located in Alrode, Alberton.

The maltings plant, which is not only a

first of its kind in Africa, will be the biggest

in Africa and third biggest in the world and

saw the congregation of a multicultural

design and construction team join SAB:

Malteurope and Hatch Goba. WBHO was

appointed to carry out all civil works on

the project.

WBHO kicked off construction in May

2014. The site team consisted of 31 foreman,

450 labour and 15 managerial staff. The orig-

inal scope of work was priced at R131-mil-

lion and was to last 12 months. After addi-

tional scope of work was included, the

contract value has increased to R190-million

SAB Alrode New Malting Plant

Civil Engineering Contractors

A1

and the duration has extended to 19 months.

Construction saw an excess of 13 000 m²

of structural concrete placed, and consisted

of 6 500 m² of formwork to bases and ground

beams, 10 000 m² of horizontal formwork

and 30 000 m² of vertical formwork. Five

tower cranes were erected on site, strategi-

cally planned to ensure that all areas of the

site were covered and wall formwork could

be placed and removed from all locations.

Due to the soil conditions on site (high

clay content with poor bearing capacity),

structures were designed to be supported

on piles. All floor slabs were designed as

suspended slabs and due to potential

heaving of the clay subgrade, a void below

ground slabs was required.

For the construction of the 6 000 m²

concrete slab for a silo terrace, a conven-

tional reinforced concrete slabwas designed.

Due to the nature of the in-situ material,

a 1 000 mm deep RC slab was required.

The opportunity for precast elements

was identified during the early phases of

construction, which saw the construction of

65 precast elements the majority of which

were ring beams.

Potentially the biggest risk on this

project was labour overspend and the

extremely tight programme.

Due to the soil conditions on site (high

clay content with poor bearing capacity),

structures were designed to be supported

on piles. All floor slabs were designed as

suspended slabs and due to potential

heaving of the clay subgrade, a void below

ground slabs was required.

For the construction of the 6 000 m²

concrete slab for a silo terrace, a conven-

tional reinforced concrete slabwas designed.

Due to the nature of the in-situ material,

a 1 000 mm deep RC slab was required.

A post tensioned slab was investigated and

the final solution was a 500 mm deep PT

slab designed by Chris Howes Construction.

The solution both accelerated construction

time and saved on material costs.

The opportunity for precast elements

was identified during the early phases of

construction, which saw the construction of

65 precast elements the majority of which

were ring beams.

The heart and soul of the germination

area an essential part of the malting plant,

was the germination bed walls. These

process walls required extreme attention

to detail. A total of seven germination beds,

68 m in length, 9,1 m wide and 4,9 m high

were to be constructed.

Project information

• Company entering: WBHO Construction

• Project start date: May 2014

• Project end date: December 2015

• Client: South African Breweries

• Main contractor: WBHO

• Principal agent: Hatch Goba

• Project value: R190-million