Previous Page  38 / 90 Next Page
Information
Show Menu
Previous Page 38 / 90 Next Page
Page Background

2 15

BEST

PR

O

JECTS

34

CONSTRUCTION WORLD

DECEMBER

2015

Careful planning and management of

façade cladding activities allowed

Murray & Roberts Western Cape

to gain 38 days on the construction

programme for Redefine Properties’ The

Towers project in Cape Town’s Central Busi-

ness District. An emphasis on innovation,

teamwork and safety characterised this

landmark project, which was completed in

August 2015.

Originally built in the 1970s, The Towers,

previously known as The Standard Bank

Building, consists of two towers, a 13 and

a 23 storey building complex, with a four

Building Contractors

A2

Project information

• Company entering: Murray & Roberts

Western Cape

• Project start date: 20 June 2013

• Project end date: 30 August 2015

• Client: Redefine

• Main contractor: Murray & Roberts

Western Cape

• Architect: Smuts & Boyes

• Principal agent: BFH de Jager Project

Managers

• Quantity surveyor: LDM Quantity

Surveyors

• Consulting engineer: Aurecon SA

• Subcontractor (façades): World

of Windows

• Project value: R370-million

(excluding VAT)

The Towers

storey building linking the two towers.

A planned upgrade of the complex to an

A-grade office building incorporated wrap-

ping the envelope in high performance

architectural glazing. It also involved adding

an additional 1 500 parking bays in the form

of a 13 storey parking structure between

the two towers, as well as upgrading of the

public square.

Construction commenced in April 2013,

with the parking structure columns being

constructed in the current basements. The

existing foundation of the seven storeys was

insufficient to cope with the loading of the

proposed 13 storey parking garage. New

foundations were required for the basement,

which continued to operate in the interim as

a three level parking garage for the tenants.

After construction of the founda-

tions for the new columns, a letterbox was

constructed in the existing slab above these

to facilitate the casting of the concrete for

the column. Once the first column on the

lower basement level was cast, the slab

above was back propped and a bigger aper-

ture was cut to extend the column through

the slab.

Concurrently with this operation the

existing four storey link building, situated

between the two towers and on top of the

old parking area where the columns were

being constructed, was being demolished.

The construction programme was

carefully coordinated to ensure that the

construction progressing from the basement

level upwards would simultaneously meet

with the demolition of the four storey link

building on the ground floor. Once this was

accomplished, the construction of the 14

storey garage began.

One of the interesting challenges

encountered on the project was main-

taining a column-free space in the existing

ground floor public square, with the top 10

levels of the parking structure cantilevering

13 metres over this square for a distance

of 50 metres. This was achieved with the

construction of a 55 metre span by 25 metre

high A-frame megatruss.

The truss is designed to span 50 metres,

carrying nine suspended floors by transfer-

ring the gravity load to the L-shaped shear

walls at the ends.

What is especially noteworthy is the

fact that an entirely separate, temporary

concrete structure was built, complete with

five piles, to support the A-frame until the

full frame was completed, whereafter the

temporary frame was demolished. This was

required due to the large magnitude of the

temporary loads, which would overload any

conventional back-propping system.

Once the A-frame was completed, the

tension ties and hangers were prestressed

to between 5 000 and 14 000 kN and

the bearing on the temporary columns

was released through a phased down-

ward-jacking process, using 8 000 kN flat-

jacks on top of the temporary columns.

Also entered Category

E