In October 2000, Sasol and the
Government of Mozambique signed
a Petroleum Production Agreement
for the development of the Temane and
Pande gas fields in Inhambane Province,
Mozambique. This agreement was followed
by the construction of an underground,
865 km long, high-pressure pipeline from
the Temane Central Processing Facility in
Mozambique to the Sasol Synfuels plant
at Secunda, South Africa (Mozambique
Secunda Pipeline).
This current and existing gas pipeline is
owned by the Republic of Mozambique Pipe-
line Investments Company (ROMPCO) with
Sasol, the South African and Mozambique
Project information
• Company entering: Group Five
Civil Engineering
• Project start date: 05/07/2013
• Project end date: 11/04/2015
• Client: Sasol
• Project team: Group Five Civil Engineering,
WK Construction and WorleyParsons
• Main contractor: Group Five
Civil Engineering
• Consulting engineer: WorleyParsons
• Subcontractor: WK Construction
• Project value: USD59-million
ROMPCO – Pipeline, Mozambique
governments as the main stakeholders.
The first section of this project was
awarded to Group Five Civil Engineering in
July 2013 and was successfully completed in
November 2014.
The Sasol, ROMPCO Loop Line 1 Project
consisted of the construction of a 26 inch,
127 km long, pipeline running parallel to the
existing MSP and located within the same
30 m wide servitude.
The new pipeline was looped/tied in
with the existing pipeline – increasing the
carrying capacity of the pipeline.
The overall project programme was
16 months. This included site establish-
ment of a fully functional 400 man accom-
modation camp, construction of the pipe-
line, hydrostatic testing, commissioning
and reinstatement.
Saddles, or Set-On Weights, were used to
secure the pipeline. For logistical purposes a
concrete batch plant was established on site
to cast the weights while a local laboratory
was subcontracted to test and monitor the
quality control of the concrete weights.
The pipes utilised for the pipeline were
‘free issue’ and the clients responsibility
(each 18 metre long). However some of the
pipes delivered were magnetized as a result
of the coating process during manufacture.
This resulted inmany difficulties and dramat-
ically increased the weld failure rate. It was
necessary to demagnetise the pipes tempo-
rarily in order to create a secure weld. This
was done using a degauss coil that induces
an opposing current through the coil. This
temporarily eliminates the magnetic field
while completing the weld, but returns again
slowly once the coil is removed.
The construction of the new line was
within 10 metres of the existing (opera-
tional) gas pipeline, thus blasting was not
the favoured option for the removal of rock.
At first the trenching activities caused a
number of delays. The contractor solved this
problem by procuring two TESMEC trenchers
to cut through the rocky sections.
Eight new boreholes were drilled and
sunk, each capable of delivering up to 10 000
cubes of water per hour. One of the bore-
holes was sunk purposefully for donation to
the surrounding community, Muabsa. This
borehole was equipped with a hand pump
and concrete base for water collection.
The main design innovations came into
play with the limited access of the Right
of Way (30 m width). It had to be utilised
not only for placing of the pipes (load and
stringing), welding and coating activities
but also for excavation, placing padding
material (<12 mm) separate from excavated
backfill material, placing concrete saddles
in ROW and still have enough space to lower
the pipes into the trenches. This had to be
done without causing any harm to desig-
nated wetland areas while still having access
for local and construction vehicles in both
directions at all times.
Winner