Previous Page  84 / 90 Next Page
Information
Show Menu
Previous Page 84 / 90 Next Page
Page Background

2 15

BEST

PR

O

JECTS

80

CONSTRUCTION WORLD

DECEMBER

2015

Project information

• Company entering: WBHO Construction

• Project start date: 29 October 2012

• Project end date: 31 October 2014

• Client: Redefine Properties

• Project team: 90 Grayston Drive Team

• Main contractor: WBHO Construction

• Architect: GLH Architects

• Principal agent: Betts Townsend

• Quantity surveyor: MLC Quantity Surveyors

• Consulting engineer: Sutherland

• Project value: R280-million

Afrisam Innovation Award for Sustainable Construction

E

The 90 Grayston Drive building is a 21

level office block development with

11 parking levels, one atrium level

and nine offices. It is a multi-functional

building with 19 343 m

2

of office space and

946 parking bays.

The building was designed to have a

unique and aesthetically pleasing façade

which makes it stand out above the neigh-

bouring buildings in Sandton. The external

façade cubes and rectangles on the façade

are a series of cantilevers that are protruding

in and outside of the building envelope.

The building was designed to have very

little impact on the environment. This led

the designers to opt for the use of ammonia

chillers for air conditioning and rain water

harvesting for flushing toilets.

The building has been designed to

have a double façade based on the explora-

tion and testing by Le Corbusier in the 20

th

Century. The two glass skins form a 900 mm

cavity and they are positioned so that air

flows naturally between them. This contin-

uous natural flow of air in the façade cavity

improves the energy performance of the

building in all seasons. The double façade

system also provides more insulation than

conventional types.

The architects, Grosskopff Lombart

Huyberechts & Associates opted for a new

look on the façades called ‘fritting’. This

is essentially a high resolution decora-

tive glazing with continuous lines flowing

throughout all the panels of glass.

The building is fitted with ‘intelligent

blinds’ which follow the sun throughout the

day. The façade is fitted with sensors that

track the movement of the sun and guide

the blinds to provide optimum protection

from the heat and glare so the interior stays

comfortable in all weather conditions.

In a drive to minimise the energy

footprint, the elevators were fitted with

an advanced, high speed elevator manage-

ment system which swiftly delivers the

passengers to their chosen stop while

conserving energy.

90 Grayston has been designed for

optimal power efficiency. The building

draws 1 700 kVA from the council supply and

is backed-up by two synchronised diesel

generators providing 100% standby power.

The diesel generators are fed by a bulk diesel

tank that allows 24 hours standby power

without being refilled.

A cast resin transformer located on

the roof supplies the mechanical cooling

chillers, minimising maintenance and

increasing electrical efficiency. The lighting

is integrated with motion sensors fitted in

the parking areas, common areas and rest

rooms to activate lighting when these areas

are in use.

The water system has been designed to

use water wisely and reduce waste to the

barest minimum. The building will harvest

rain water into tanks that can store up to 70

cubic metres, which will be used primarily

for toilet flushing.

The project structure programme was

essentially 21 levels in 16 months. This

appeared to be a daunting task until the

entire project team started to re-engineer

the building to achieve programme.

This process yielded changes to the

slabs from conventional reinforced concrete

slabs to post tensioned slabs, to reduce the

amount of reinforcement steel to be handled.

This led to 90 Grayston Drive being amongst

the few buildings with Post Tensioned slabs

throughout all levels.