Previous Page  80 / 90 Next Page
Information
Show Menu
Previous Page 80 / 90 Next Page
Page Background

2 15

BEST

PR

O

JECTS

76

CONSTRUCTION WORLD

DECEMBER

2015

Professional Services

C

Project information

• Company entering: Hatch Goba

• Client: eThekwini Municipality

• Project start date: March 2011

• Project end date: July 2015

• Consulting engineer: Hatch Goba

Hatch Goba and SANRAL have been

collaborating successfully for a

number of years on such flag-

ship projects as the Gillooly’s Inter-

change in Johannesburg, one of the largest

and busiest of its kind in the Southern

Hemisphere. Hatch Goba was originally

appointed by the South African National

Roads Agency (SANRAL) in 2009 to complete

the detailed design and relevant documen-

tation for the extensive upgrade of the inter-

change. Construction commenced in March

2011 and was expected to be complete at

the end of July 2015.

Umgeni Road has been a major trans-

port hub for decades, and has seen consid-

erable urban development over the years.

This meant that a major consideration was

to minimise traffic disruption during the

construction phase along the N2 and M19

major routes. Another constraint was posed

by the Umgeni River, along with existing

commercial and residential areas that had

to be accommodated.

To overcome these challenges, two

directional ramps were built by means of the

incremental launch construction method.

While this by itself is not new, having

to design and construct using extremely

tight radii on a global curve was a com-

plex process.

This entailed the entire bridge deck

being built from one end of the structure,

as opposed to the traditional segmental

construction method where the bridge is

built one span at a time. The application of

this innovative technology had a substantial

impact on the construction requirements, as

well as minimising traffic disruption.

The 20-m-high elevated casting yard,

combined with the stunning sight of the

two incremental launch bridges being

constructed at the same time and crossing

each other, was a first in South Africa and

attracted a lot of attention.

The three bridge decks over Umgeni

Road were designed to include precast

beams to minimise disruption to traffic

during construction. Twelve 30 m and twen-

ty-three 20-m-long beams were constructed

off-site and erected during overnight road

closures. The remaining bridge decks were

cast in situ.

Particular attention was paid to the

aesthetics of the concrete structures during

design and construction.

The bridge pier heads were designed

to have elegant and fluted shapes. The

excellent quality of the concrete finishes

produced has enhanced the appearance and

Umgeni Road Interchange Project

durability of the structures on this project.

The overall bridge works were 1 200 m

long, with a surface area of 14 000 m

2

. The

roadworks alone comprised 56 000 m

2

of

asphalt, while the bulk earthworks totalled

100 000 m

3

of cut material and 200 000 m

3

of fill material.

Another major challenge was posed

by the fact that a large quantity of existing

services not only had to be relocated, but

had to be searched for and identified. These

ranged from electricity, Transnet and water

reticulation to sewerage and telecommuni-

cations infrastructure. This was an excep-

tionally demanding and challenging process.

Hatch Goba monitored the project

continually to ensure correct procedures

were followed. This was in order to avoid

negative impacts on the environment, such

as extensions of construction time on the

project, materials used and product wastage

or disposal.

Concrete trucks were returned to the

Roadhouse plant in the Umgeni Area to

release any extra concrete on a daily basis so

as not to leave any material behind on-site.

eThekwini Municipality undertook monthly

checks/audits to ensure the impact on the

environment was kept to a minimum.

The completed Umgeni Interchange

upgrade project has significantly alleviated

traffic congestion by allowing the free flow of

about 14 000 vehicles during morning peak

hour and about 16 000 vehicles during after-

noon peak hour.