Previous Page  77 / 90 Next Page
Information
Show Menu
Previous Page 77 / 90 Next Page
Page Background

73

CONSTRUCTION WORLD

DECEMBER

2015

2 15

BEST

PR

O

JECTS

Project information

• Comany entering: UWP Consulting

• Project start date: 14 October 2013

• Project end date: 10 June 2015

• Client: uMkhanyakude District Municipality

• Main contractor: Icon Construction/Veolia

Joint Venture

• Consulting engineer: UWP Consulting

• Project value: R125-million

UWP Consulting was appointed in

April 2011 to commence planning

of the Shemula Bulk Water Supply

Scheme Upgrade, a R845-million bulk

water supply scheme to serve 230 000

people in the northern half of the Jozini and

Umhlabuyalingana Municipalities.

During the preliminary design, the client

decided that the water works itself should

be let as an EPC (turnkey) tender. Certain

elements of the design had already reached

an advanced stage and it was decided to

split the contract into two sub-phases.

Phase IA, a conventional EPCM contract,

included the raw water pumpstation and

rising main, the clear water storage reser-

voir and the clear water pumpstation and

rising main. Phase IB, an EPC contract,

included the full water treatment works

design and construction.

The design of Phase IA was carried out

by UWP while the design of Phase IB was

carried out by the contractor. UWP prepared

a detailed specification for the turnkey

tender to ensure that a state-of-the-art

facility was provided under the EPC contract.

The raw water pumpstation has been

designed as a dry well and consists of a

9 m deep x 7 m diameter concrete structure

embedded in the left bank of the Pongola

River. Generally the flow in the river is kept

constant at 5 cumec and is controlled at the

Pongolapoort Dam some 60 km upstream.

However every September DWS releases

a controlled flood peaking at 600 cumec.

During the flood the water level rises to

within 2 m of the roof of the pumpstation.

To allow for a variable flow rate into the

head of the waterworks in the absence of a

raw water reservoir, variable speed drives

controlled by the works operator were

installed on the raw water pumpsets. Allow-

ance has been made to install larger pumps

when the works is increased from 20 Mℓ/day

to 40 Mℓ/day.

The waterworks layout allows for the

smallest feasible footprint. Emphasis was on

simplicity of operation, operational control

Shemula Water Project – Upgrade:

Phase I – Shemula Water Treatment Works

and maintenance, high performance effi-

ciency and stability together with reliability,

flexibility and economy of operation, as well

as a pleasant working environment.

One of the main design features was

using natural slope of the land to eliminate

the need for any pumping requirements

withintheplantandhencesaveonelectricity.

The filters discharge potable water from

the clearwell directly into the 2,5 Mℓ clear

water reservoir from where a 700 mm dia-

meter gravity main conveys water to the

clear water pumpstation.

The clear water pumpstation, pipework

and rising main have been sized to cater for

the ultimate demand. Allowance has been

made to add a further two pumps alongside

the current four when the plant is upgraded

to 40 Mℓ/day.

The pumps operate at a working pres-

sure of 20 bar and deliver water via a 2 500 m

long x 700 mm diameter GRP rising main to

the existing 4,5 Mℓ command reservoir from

where an existing bulk distribution system

distributes water.

The existing bulk distribution system

is severely undersized and in very poor

condition and Phases 2 to 6 of the scheme

will include bulk pipelines from 700 mm Ø

to 200 mm Ø, terminal reservoirs and

booster pump stations to supply water to

the entire region.