Previous Page  22 / 68 Next Page
Information
Show Menu
Previous Page 22 / 68 Next Page
Page Background

CONSTRUCTION WORLD

APRIL

2017

20

PROJECTS & CONTRACTS

Cornelis Grotius, general manager

Johnson Renew, says that the current

contract to supply cranes and support

services for installation of 67 wind turbines

started in May 2016 and is expected to have

an eight month duration.

Being constructed by EPC Longyuan

Engineering South Africa, the Longyuan

Mulilo De Aar Maanhaarberg Wind Energy

Facility project is a 96,5 MW wind energy

facility. Longyuan Engineering South Africa,

of which a local Community Education Trust

has a 30% shareholding, is a subsidiary

of China Longyuan. The wind turbine

generators are being supplied from China

by Guodian United Power Corporation.

Grotius says the wind turbine

components are offloaded on the

installation pads ready for the heavy lift

programme to begin. These lifts are done

using a 250 t mobile crane. The heavy lift

programme starts with the pre-installation

of the bottom tower sections using a

combination of a 550 t crane and a

100 t crane.

The main installation lifting will be done

with a 1 200 t hydraulic crawler crane used

in combination with a 100 t crane.

“As a subsidiary of Johnson Crane Hire,

Johnson Renew has ready access to the

depth of its parent company’s crane fleet

which allows it to supply these different

crane combinations,” Grotius says. “This

is a major differentiator in the market and

allows us to customise lifting packages for

individual projects.”

Significantly, the LTR 11200 is the fleet’s

newest crawler crane and was selected to

undertake the main installation lifts due to

its narrow track crawler undercarriage and

100 metre hydraulic boom. This technology

allows the machine to move and set up

relatively rapidly between installation pads

with the added advantage of travelling on

narrow access roads. This will assist in

increasing the productivity on the project.

Commenting on the challenges on this

particular site, Grotius says that there are

a number of very steep hills resulting in

potentially difficult terrain in which to work.

Undertaking heavy lifts difficult

conditions is not new for Johnson Renew.

“We have an established track record with

challenging conditions and will be able to

leverage our resident expertise in heavy

lifting and wind farm project experience

to ensure that we meet the construction

programme safely,” Grotius says.

Preparing for any lift includes a full

assessment of the on-site conditions as

well as route surveys. All this is done in

close collaboration with both the client and

the crane OEM to ensure all aspects are

factored into the lifting solution.

“Upfront planning enables our heavy lift

team to select the most appropriate crane

configuration for the task at hand which

in this case is the new LTR 11200 crawler

crane,” he says.

“It is by understanding our crane fleet

and how these machines can be adapted

for specific site conditions that we are able

to optimise the lifting solution and produce

the results we do, and with an impeccable

safety record.”

This knowledge comes with years of

experience, and ensuring that all operators

are skilled and competent. “Ongoing

operator training also plays an important

role in adapting the lifting operation to site

specific conditions,” he says.

LIFTING

De Aar

wind farm

TURBINES

Challenging conditions are considered normal for

Johnson Renew, and its contract at De Aar 1 Wind

Farm showcased how this subsidiary of Johnson

Crane Hire overcomes these with ease.

ABOVE:

Johnson Crane Hire’s LTR 11200

crawler crane in action.

LEFT:

Johnson Crane Hire's new LTR

11200 was selected to undertake the

main installation lifts due to its narrow

track crawler undercarriage and 100 metre

hydraulic boom.