Previous Page  48 / 68 Next Page
Information
Show Menu
Previous Page 48 / 68 Next Page
Page Background

CONSTRUCTION WORLD

APRIL

2017

46

WASTE MANAGEMENT AND RECYCLING

Situated close to the Helios substation in

the Hantam Municipality, when completed

these two wind farms will boast a total of

122 wind turbine generators between them

and each will feed 563 500 MWh of clean

renewable energy into the national grid.

The Loeriesfontein Wind Farm and

the Khobab Wind Farm were constructed

by Murray & Roberts Construction in a

consortium with CONCO. Significantly,

the two companies also successfully

completed the construction of the Noupoort

Wind Farm for operator, Mainstream

Renewable Power South Africa.

An arid region

“Constructing such important projects in

this remote location called for innovative

thinking on our part,” Stephan Venter,

project manager for Murray & Roberts

Infrastructure, says. Boesmanland in the

Northern Cape is an arid region, which has

been further exacerbated by the grips of

a severe drought making the availability

of water a major challenge for all. As a

result of this major water scarcity, limited

extraction rates were allowed in the Water

Use Licences.

Venter says that the water shortage and

low extraction limit was taken into account

by the Murray & Roberts Infrastructure

team, and an intense water management

plan aimed at reducing water consumption

was put into place.

Marli van Rooy, environmental officer

for Murray & Roberts Infrastructure on the

project, says that the main strategy was

to reuse as much of the water under the

company’s control as possible as this

would reduce the need to source additional

water supply.

As part of the initiative, Murray &

Roberts Infrastructure installed a modular

water treatment plant on site. The plant

has a screening system which removes

the heaviest solids, while bacteriological

rollers treat the remainder. Significantly, no

chemicals are used during the process.

“Having the plant allowed the treatment

of grey and black water generated on site

and the reuse of this recycled water for

construction purposes,” Van Rooy explains.

Majority of the recycled water was

used on the earthwork layers for the wind

turbine bases. On average, the treatment

plant cleaned 30 000 litres per day and the

treated water was stored in two reservoirs

for reuse.

Another initiative aimed specifically

at reducing water consumption was the

construction of a specialised wash bay

solution at the on-site batch plant. “Wash-

ing the drums of readymix concrete trucks

is a necessity on any construction site, but

wasting water is not,” Van Rooy explains.

The wash bay comprises a series of

settlement ponds, with each having an

overflow which reports to the next pond

once it reaches a certain level. The concrete

sludge settles in the pond and once this

happens it is removed manually and left on

a specially constructed bunded slab to dry.

“This resultant dried material was removed

INNOVATIVE

environmental

INITIATIVES

An innovative approach saw

several impressive environmental

initiatives implemented by

Murray & Roberts Infrastructure

on the Loeriesfontein Wind Farm

and Khobab Wind Farm project in

the Northern Cape.

Marli van Rooy, environmental officer for Murray & Roberts Infrastructure, outside the modular water treatment plant installed by the company.

“On a site as remote as this, soil contamination

can be an extreme challenge as there are further

complications including the distances to the nearest

hazardous landfill site which is in Cape Town.”