TAR NC Implementation Document – Second Edition September 2017 |

159

Chapter I:

Who Is Doing What

Table 20 includes the obligations in the TAR NC by

‘actor’: TSO/NRA, TSO, NRA, ENTSOG, ACER and

the EC. The obligations are listed in the order of their

appearance in the TAR NC.

The obligations highlighted in blue are not in Chapter II ‘General timeline’ below. The

obligations with an asterisk are only indicated on the timeline for ‘Multi-TSO

arrangements within a MS’ in Chapter II ‘General timeline’ below.

WHO IS DOING WHAT

Who

Ref. to the NC What to do

When to do

Application Date

I.

TSO/NRA,

as decided

by NRA

1. Article 5(1),

ref. to Article 26

Perform and publish CAA as part of the final consulta-

tion per Article 26

Part of the final consultation

per Article 26

Rule – 6 April 2017,

compliance – 31 May 2019

2. Article 26 Carry out the periodic consultations: one or more

‘intermediate’ consultations (optional, covers some/all

elements in Article 26(1)) + final consultation

(obligatory, covers all elements in Article 26(1))

Prepare consultation document(s) in English, to the

extent possible

As from the NC entry into force

Min duration of consultation –

2 months

Rule – 6 April 2017,

compliance – 31 May 2019

3. Article 26(3) Publish the responses and their summary from the

consultation referred to in point 2

Prepare the summary in English, to the extent possible

Within 1 month following the

end of consultation referred to

in point 2

Rule – 6 April 2017,

compliance – 31 May 2019

4. Article 27(1) Forward the final consultation document(s) to ACER Upon launching the final

consultation and prior to deci-

sion referred to in point III.18

Rule – 6 April 2017,

compliance – 31 May 2019

5. Article 29 Publish the information before the annual yearly

capacity auction

Min 30 days before the annual

yearly capacity auction

Rule – 1 October 2017,

compliance – June 2018

and every year thereafter

6. Article 30 Publish the information before the tariff period

Min 30 days before the tariff

period

Rule – 1 October 2017,

compliance – depending on

the tariff period and every

year thereafter

II.

TSO

1. Article 21(3) Agree on the attribution of the auction premium from

the sales of bundled capacity products (unless such

agreement is in place and approved)

Before the approval referred to

in point III.14, not a yearly ac-

tivity unless there are changes

to the agreement

6 April 2017

2. Article 35(3) Send the contracts or the information on capacity

bookings to NRA for information – where the transmis-

sion tariff level foreseen in such contracts is grandfa-

thered

Within 1 month as from the NC

entry into force

Rule – 6 April 2017,

compliance – 6 May 2017

3. Article

36(2)(a)

Submit to ENTSOG all information required by ENTSOG

as regards to compliance with Chapter VIII of the NC

31 December 2017

Rule – 6 April 2017,

compliance – 31 December

2017

4. Article

36(2)(b)

Submit to ENTSOG all information required by ENTSOG

as regards to compliance with Chapters other than

Chapter VIII of the NC

31 December 2019

Rule – 6 April 2017,

compliance – 31 December

2019

5. Article

37(1)-(2)

Entity which operates an interconnector may request

an exemption from one/more NC Articles, include in

the request a detailed reasoning, supporting docu-

ments and, where appropriate, CBA

As from entry into force

Rule – 6 April 2017,

compliance – depending on

the date of application for

an exemption